Assessment Year | 2003 |
---|---|
Principal Product | Stainless Steel Floats |
NAICS | 332618: Other Fabricated Wire Product Manufacturing |
SIC | 3496: Miscellaneous Fabricated Wire Products |
Sales Range | $1 M to 5M |
# of Employees | 23 |
Plant Area |
29,000
ft2
|
Annual Production | 36,000
pieces
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $10,554 | 207,480 |
kWh
|
$0.051 |
Electricity Demand | $16,517 | 1,351 |
kW-mo/yr
|
$12.23 |
Electricity Fees | $929 | - |
|
- |
Natural Gas | $11,962 | 2,152 |
MMBtu
|
$5.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $3,795 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,877 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,535 | $6,726 |
$625
14,582
kWh
|
$746
-
kW-mo/yr
|
$66 | $98 | |
02 | 2.7135: Install occupancy sensors | $136 | $141 |
$110
2,561
kWh
|
$26
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,877 | $2,600 |
$859
19,867
kWh
|
$1,018
-
kW-mo/yr
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $185 | $150 |
$55
1,280
kWh
|
$130
-
kW-mo/yr
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $62 | - |
$28
656
kWh
|
$34
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $3,795 | $9,617 |
$1,677
38,946
kWh
|
$1,954
-
kW-mo/yr
|
$66 | $98 | ||
TOTAL IMPLEMENTED | $1,877 | $2,600 |
$859
19,867
kWh
|
$1,018
-
kW-mo/yr
|
- | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs