ITAC Assessment: IC0034
ITAC logo
ITAC Assessment: IC0034
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Trade Bindery
NAICS
n/a
SIC 2789: Bookbinding and Related Work
Sales Range $5
M
to 10
M
# of Employees 87
Plant Area 80,000
ft2
Annual Production 30,000,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $32,301 840,366
kWh
Electricity Demand $8,538 2,468
kW-mo/yr
Electricity Fees $24,104 -
Natural Gas $40,524 4,572
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $43,909 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,566

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,466 $800 $2,245
34,016
kWh
$221
-
kW-mo/yr
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $14,405 $30,975 $14,448
218,912
kWh
$1,038
-
kW-mo/yr
- $(-759.0) $(-322.0)
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,990 $8,449 $2,407
36,477
kWh
$173
-
kW-mo/yr
- $128 $282
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,772 $7,610 $6,336
65,998
kWh
$436
-
kW-mo/yr
- - -
05 2.4231: Reduce the pressure of compressed air to the minimum required $677 - $573
8,689
kWh
$104
-
kW-mo/yr
- - -
06 2.1116: Improve combustion control capability $5,715 $18,850 - - $5,715
-
MMBtu
- -
07 2.6232: Install set-back timers $461 $581 - - $461
-
MMBtu
- -
08 3.7311: Maintain machines to reduce leaks $10,423 - - - - $10,400 $23
TOTAL RECOMMENDED $43,909 $67,265 $26,009
364,092
kWh
$1,972
-
kW-mo/yr
$6,176
-
MMBtu
$9,769 $(-17.0)
TOTAL IMPLEMENTED $13,566 $800 $2,818
42,705
kWh
$325
-
kW-mo/yr
- $10,400 $23
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs