Assessment Year | 2002 |
---|---|
Principal Product | Trade Bindery |
NAICS |
n/a
|
SIC | 2789: Bookbinding and Related Work |
Sales Range | $5 M to 10M |
# of Employees | 87 |
Plant Area |
80,000
ft2
|
Annual Production | 30,000,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $32,301 | 840,366 |
kWh
|
$0.038 |
Electricity Demand | $8,538 | 2,468 |
kW-mo/yr
|
$3.46 |
Electricity Fees | $24,104 | - |
|
- |
Natural Gas | $40,524 | 4,572 |
MMBtu
|
$8.86 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $43,909 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,566 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,466 | $800 |
$2,245
34,016
kWh
|
$221
-
kW-mo/yr
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,405 | $30,975 |
$14,448
218,912
kWh
|
$1,038
-
kW-mo/yr
|
- | $(-759.0) | $(-322.0) | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,990 | $8,449 |
$2,407
36,477
kWh
|
$173
-
kW-mo/yr
|
- | $128 | $282 | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,772 | $7,610 |
$6,336
65,998
kWh
|
$436
-
kW-mo/yr
|
- | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $677 | - |
$573
8,689
kWh
|
$104
-
kW-mo/yr
|
- | - | - | |
06 | 2.1116: Improve combustion control capability | $5,715 | $18,850 | - | - |
$5,715
-
MMBtu
|
- | - | |
07 | 2.6232: Install set-back timers | $461 | $581 | - | - |
$461
-
MMBtu
|
- | - | |
08 | 3.7311: Maintain machines to reduce leaks | $10,423 | - | - | - | - | $10,400 | $23 | |
TOTAL RECOMMENDED | $43,909 | $67,265 |
$26,009
364,092
kWh
|
$1,972
-
kW-mo/yr
|
$6,176
-
MMBtu
|
$9,769 | $(-17.0) | ||
TOTAL IMPLEMENTED | $13,566 | $800 |
$2,818
42,705
kWh
|
$325
-
kW-mo/yr
|
- | $10,400 | $23 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs