ITAC Assessment: AS0104
ITAC logo
ITAC Assessment: AS0104
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product PORTLAND CEMENT
NAICS
n/a
SIC 3241: Cement, Hydraulic
Sales Range $50
M
to 100
M
# of Employees 145
Plant Area
n/a
Annual Production 1,500,000
ton
Production Hrs. Annual 8,736
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $6,942,370 104,315,359
kWh
Natural Gas $277,507 62,691
MMBtu
Coal $3,442,583 2,063,542
MMBtu
Other Energy $137,034 103,211
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $402,780 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,027 - $1,248
18,757
kWh
- $(-221.0)
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,926 $3,600 $1,926
29,015
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $580 $369 $580
8,792
kWh
- -
04 2.7135: Install occupancy sensors $1,134 $1,021 $1,134
16,999
kWh
- -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $9,642 - $9,642
144,783
kWh
- -
06 2.4133: Use most efficient type of electric motors $6,448 $7,084 $6,448
97,011
kWh
- -
07 2.3192: Use fossil fuel powered generator during peak demand periods $382,023 $1,218,600 $1,044,071
17,791,618
kWh
$(-751,006.0)
-
MMBtu
$88,958
TOTAL RECOMMENDED $402,780 $1,230,674 $1,065,049
18,106,975
kWh
$(-751,006.0)
-
MMBtu
$88,737
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs