| Assessment Year | 1993 |
|---|---|
| Principal Product | PORTLAND CEMENT |
| NAICS |
n/a
|
| SIC | 3241: Cement, Hydraulic |
| Sales Range | $50 M to 100M |
| # of Employees | 145 |
| Plant Area |
n/a
|
| Annual Production | 1,500,000
ton
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $6,942,370 | 104,315,359 |
kWh
|
$0.067 |
| Natural Gas | $277,507 | 62,691 |
MMBtu
|
$4.43 |
| Coal | $3,442,583 | 2,063,542 |
MMBtu
|
$1.67 |
| Other Energy | $137,034 | 103,211 |
MMBtu
|
$1.33 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $402,780 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,027 | - |
$1,248
18,757
kWh
|
- | $(-221.0) | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,926 | $3,600 |
$1,926
29,015
kWh
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $580 | $369 |
$580
8,792
kWh
|
- | - | |
| 04 | 2.7135: Install occupancy sensors | $1,134 | $1,021 |
$1,134
16,999
kWh
|
- | - | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $9,642 | - |
$9,642
144,783
kWh
|
- | - | |
| 06 | 2.4133: Use most efficient type of electric motors | $6,448 | $7,084 |
$6,448
97,011
kWh
|
- | - | |
| 07 | 2.3192: Use fossil fuel powered generator during peak demand periods | $382,023 | $1,218,600 |
$1,044,071
17,791,618
kWh
|
$(-751,006.0)
-
MMBtu
|
$88,958 | |
| TOTAL RECOMMENDED | $402,780 | $1,230,674 |
$1,065,049
18,106,975
kWh
|
$(-751,006.0)
-
MMBtu
|
$88,737 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs