Assessment Year | 2001 |
---|---|
Principal Product | Screen Printed Banners & POP Displays |
NAICS |
n/a
|
SIC | 2399: Fabricated Textile Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 65 |
Plant Area |
60,000
ft2
|
Annual Production | 2,500,000
pieces
|
Production Hrs. Annual | 2,496
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $38,012 | 1,087,724 |
kWh
|
$0.035 |
Electricity Demand | $104,794 | 8,264 |
kW-mo/yr
|
$12.68 |
Electricity Fees | $10,775 | - |
|
- |
Natural Gas | $69,941 | 8,570 |
MMBtu
|
$8.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $88,599 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $159 | $245 |
$60
1,700
kWh
|
$99
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $996 | $2,273 |
$235
6,728
kWh
|
$112
-
kW-mo/yr
|
- | $470 | - | $179 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,581 | $24,034 |
$1,668
47,647
kWh
|
$2,913
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.2511: Insulate bare equipment | $1,227 | $2,450 | - | - |
$1,227
-
MMBtu
|
- | - | - | |
05 | 2.2437: Recover waste heat from equipment | $1,736 | $2,070 | - | - |
$1,736
-
MMBtu
|
- | - | - | |
06 | 4.322: Eliminate old stock and modify inventory control | $22,400 | $6,000 | - | - | - | - | $22,400 | - | |
07 | 4.447: Automate payroll system | $57,500 | $8,600 | - | - | - | $55,500 | $2,000 | - | |
TOTAL RECOMMENDED | $88,599 | $45,672 |
$1,963
56,075
kWh
|
$3,124
-
kW-mo/yr
|
$2,963
-
MMBtu
|
$55,970 | $24,400 | $179 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs