ITAC Assessment: IC0012
ITAC logo
ITAC Assessment: IC0012
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Screen Printed Banners & POP Displays
NAICS
n/a
SIC 2399: Fabricated Textile Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 65
Plant Area 60,000
ft2
Annual Production 2,500,000
pieces
Production Hrs. Annual 2,496
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,012 1,087,724
kWh
Electricity Demand $104,794 8,264
kW-mo/yr
Electricity Fees $10,775 -
Natural Gas $69,941 8,570
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $88,599 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4221: Install compressor air intakes in coolest locations $159 $245 $60
1,700
kWh
$99
-
kW-mo/yr
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $996 $2,273 $235
6,728
kWh
$112
-
kW-mo/yr
- $470 - $179
03 2.7142: Utilize higher efficiency lamps and/or ballasts $4,581 $24,034 $1,668
47,647
kWh
$2,913
-
kW-mo/yr
- - - -
04 2.2511: Insulate bare equipment $1,227 $2,450 - - $1,227
-
MMBtu
- - -
05 2.2437: Recover waste heat from equipment $1,736 $2,070 - - $1,736
-
MMBtu
- - -
06 4.322: Eliminate old stock and modify inventory control $22,400 $6,000 - - - - $22,400 -
07 4.447: Automate payroll system $57,500 $8,600 - - - $55,500 $2,000 -
TOTAL RECOMMENDED $88,599 $45,672 $1,963
56,075
kWh
$3,124
-
kW-mo/yr
$2,963
-
MMBtu
$55,970 $24,400 $179
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs