ITAC Assessment: AT0085
ITAC logo
ITAC Assessment: AT0085
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product CHAIRS
NAICS
n/a
SIC 2521: Wood Office Furniture
Sales Range $10
M
to 50
M
# of Employees 245
Plant Area
n/a
Annual Production 100,000
pieces
Production Hrs. Annual 2,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $116,515 1,662,954
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,875 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,106

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $769 $394 $769
10,844
kWh
-
02 2.7226: Use computer programs to optimize hvac performance $2,616 $6,000 $2,616
37,222
kWh
-
03 2.5194: Redesign process $6,403 - $1,403
19,930
kWh
$5,000
04 2.6212: Turn off equipment during breaks, reduce operating time $804 $1,800 $804
11,430
kWh
-
05 2.4133: Use most efficient type of electric motors $480 $731 $480
6,741
kWh
-
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,133 - $1,133
16,120
kWh
-
07 2.4312: Improve lubrication practices $670 - $670
9,672
kWh
-
TOTAL RECOMMENDED $12,875 $8,925 $7,875
111,959
kWh
$5,000
TOTAL IMPLEMENTED $12,106 $8,531 $7,106
101,115
kWh
$5,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs