Assessment Year | 2001 |
---|---|
Principal Product | Fabricated Metal Parts |
NAICS |
n/a
|
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 280 |
Plant Area |
140,000
ft2
|
Annual Production | 5,000,000
pieces
|
Production Hrs. Annual | 4,590
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $101,205 | 2,451,054 |
kWh
|
$0.041 |
Electricity Demand | $85,752 | 6,792 |
kW-mo/yr
|
$12.63 |
Electricity Fees | $16,057 | - |
|
- |
Natural Gas | $20,245 | 2,345 |
MMBtu
|
$8.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $950,692 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $23,962 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,919 | $1,100 |
$1,457
35,274
kWh
|
$1,462
-
kW-mo/yr
|
- | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $730 | $3,200 |
$376
9,099
kWh
|
$354
-
kW-mo/yr
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $20,217 | $65,216 |
$8,729
211,368
kWh
|
$11,488
-
kW-mo/yr
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $826 | $2,328 |
$207
5,021
kWh
|
$88
-
kW-mo/yr
|
$410 | - | $121 | |
05 | 4.652: Replace existing equipment with more suitable substitutes | $224,000 | $9,200 | - | - | $163,000 | $61,000 | - | |
06 | 4.322: Eliminate old stock and modify inventory control | $702,000 | $8,500 | - | - | - | $702,000 | - | |
TOTAL RECOMMENDED | $950,692 | $89,544 |
$10,769
260,762
kWh
|
$13,392
-
kW-mo/yr
|
$163,410 | $763,000 | $121 | ||
TOTAL IMPLEMENTED | $23,962 | $68,644 |
$10,393
251,663
kWh
|
$13,038
-
kW-mo/yr
|
$410 | - | $121 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs