Assessment Year | 2001 |
---|---|
Principal Product | Point of Purchase Displays |
NAICS |
n/a
|
SIC | 3993: Signs and Advertising Specialties |
Sales Range | $10 M to 50M |
# of Employees | 85 |
Plant Area |
130,000
ft2
|
Annual Production | 45,000
pieces
|
Production Hrs. Annual | 4,290
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $30,113 | 828,083 |
kWh
|
$0.036 |
Electricity Demand | $36,433 | 2,964 |
kW-mo/yr
|
$12.29 |
Electricity Fees | $7,732 | - |
|
- |
Natural Gas | $76,816 | 12,805 |
MMBtu
|
$6.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $77,367 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,749 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,749 | $1,150 |
$2,429
67,472
kWh
|
$2,320
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4226: Use / purchase optimum sized compressor | $3,491 | $10,553 |
$3,012
83,660
kWh
|
$479
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.3132: Recharge batteries on during off-peak demand periods | $737 | - | - |
$737
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,197 | - | - |
$2,197
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $593 | $1,804 |
$159
4,415
kWh
|
- | - | $361 | - | $73 | |
06 | 3.5316: Contract a wood pallet recycling company | $5,600 | - | - | - |
$5,600
-
lb
|
- | - | - | |
07 | 4.426: Modify workload | $60,000 | $4,000 | - | - | - | $44,000 | $16,000 | - | |
TOTAL RECOMMENDED | $77,367 | $17,507 |
$5,600
155,547
kWh
|
$5,733
-
kW-mo/yr
|
$5,600
-
lb
|
$44,361 | $16,000 | $73 | ||
TOTAL IMPLEMENTED | $4,749 | $1,150 |
$2,429
67,472
kWh
|
$2,320
-
kW-mo/yr
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs