ITAC Assessment: IC0002
ITAC logo
ITAC Assessment: IC0002
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Agricultural Chemicals
NAICS
n/a
SIC 2879: Pesticides and Agricultural Chemicals, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 70
Plant Area 136,000
ft2
Annual Production 4,000
Tgal
Production Hrs. Annual 5,344
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $61,254 1,797,840
kWh
Electricity Demand $57,946 4,800
kW-mo/yr
Electricity Fees $12,174 -
Natural Gas $47,339 12,874
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $754,155 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,638

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,638 $600 $1,478
43,520
kWh
$1,160
-
kW-mo/yr
- - - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $674 - $370
11,000
kWh
$304
-
kW-mo/yr
- - - -
03 2.4221: Install compressor air intakes in coolest locations $770 $500 $420
12,600
kWh
$350
-
kW-mo/yr
- - - -
04 2.4133: Use most efficient type of electric motors $552 $979 $296
8,697
kWh
$256
-
kW-mo/yr
- - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $19,521 $95,073 n/a $8,296
243,987
kWh
$11,225
-
kW-mo/yr
- - - -
06 4.111: Add equipment/ operators to reduce production bottleneck $730,000 $2,950,000 n/a - - $70,000
-
Tgal
$480,000 $56,000 $124,000
TOTAL RECOMMENDED $754,155 $3,047,152 $10,860
319,804
kWh
$13,295
-
kW-mo/yr
$70,000
-
Tgal
$480,000 $56,000 $124,000
TOTAL IMPLEMENTED $2,638 $600 $1,478
43,520
kWh
$1,160
-
kW-mo/yr
- - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs