Assessment Year | 2001 |
---|---|
Principal Product | Agricultural Chemicals |
NAICS |
n/a
|
SIC | 2879: Pesticides and Agricultural Chemicals, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
136,000
ft2
|
Annual Production | 4,000
Tgal
|
Production Hrs. Annual | 5,344
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $61,254 | 1,797,840 |
kWh
|
$0.034 |
Electricity Demand | $57,946 | 4,800 |
kW-mo/yr
|
$12.07 |
Electricity Fees | $12,174 | - |
|
- |
Natural Gas | $47,339 | 12,874 |
MMBtu
|
$3.68 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $754,155 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,638 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,638 | $600 |
$1,478
43,520
kWh
|
$1,160
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $674 | - |
$370
11,000
kWh
|
$304
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $770 | $500 |
$420
12,600
kWh
|
$350
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $552 | $979 |
$296
8,697
kWh
|
$256
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $19,521 | $95,073 | n/a |
$8,296
243,987
kWh
|
$11,225
-
kW-mo/yr
|
- | - | - | - |
06 | 4.111: Add equipment/ operators to reduce production bottleneck | $730,000 | $2,950,000 | n/a | - | - |
$70,000
-
Tgal
|
$480,000 | $56,000 | $124,000 |
TOTAL RECOMMENDED | $754,155 | $3,047,152 |
$10,860
319,804
kWh
|
$13,295
-
kW-mo/yr
|
$70,000
-
Tgal
|
$480,000 | $56,000 | $124,000 | ||
TOTAL IMPLEMENTED | $2,638 | $600 |
$1,478
43,520
kWh
|
$1,160
-
kW-mo/yr
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs