Assessment Year | 2016 |
---|---|
Principal Product | Agricultural Steel Products |
NAICS | 333111: Farm Machinery and Equipment Manufacturing |
SIC | 3523: Farm Machinery and Equipment |
Sales Range | $100 M to 500M |
# of Employees | 500 |
Plant Area |
700,000
ft2
|
Annual Production | 120,000,000
lb
|
Production Hrs. Annual | 4,590
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $423,403 | 10,706,830 |
kWh
|
$0.040 |
Electricity Demand | $140,273 | 27,876 |
kW-mo/yr
|
$5.03 |
Electricity Fees | $9,174 | - |
|
- |
Natural Gas | $37,526 | 10,501 |
MMBtu
|
$3.57 |
LPG | $99,911 | 14,536 |
MMBtu
|
$6.87 |
TOTAL YEARLY COSTS | $710,287 | |||
RECOMMENDED SAVINGS* | $66,553 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,792 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $54,062 | $60,264 |
$40,014
1,047,405
kWh
|
$14,048
-
kW-mo/yr
|
- | |
02 | 2.7135: Install occupancy sensors | $3,083 | $5,550 |
$3,083
80,704
kWh
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,616 | $5,218 |
$1,924
50,424
kWh
|
$692
-
kW-mo/yr
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $2,371 | $500 |
$1,771
46,360
kWh
|
$600
-
kW-mo/yr
|
- | |
05 | 2.2437: Recover waste heat from equipment | $1,846 | $2,352 | - | - |
$1,846
-
MMBtu
|
|
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,529 | $165 |
$1,139
29,788
kWh
|
$390
-
kW-mo/yr
|
- | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,046 | $70 |
$794
20,790
kWh
|
$252
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $66,553 | $74,119 |
$48,725
1,275,471
kWh
|
$15,982
-
kW-mo/yr
|
$1,846
-
MMBtu
|
||
TOTAL IMPLEMENTED | $6,792 | $3,087 |
$3,704
96,938
kWh
|
$1,242
-
kW-mo/yr
|
$1,846
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs