| Assessment Year | 2016 |
|---|---|
| Principal Product | Potable Water |
| NAICS | 221310: Water Supply and Irrigation Systems |
| SIC | 4941: Water Supply |
| Sales Range | $10 M to 50M |
| # of Employees | 235 |
| Plant Area |
278,500
ft2
|
| Annual Production | 9,751,000
Tgal
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $582,336 | 16,336,711 |
kWh
|
$0.036 |
| Electricity Demand | $118,821 | 33,036 |
kW-mo/yr
|
$3.60 |
| Electricity Fees | $85,224 | - |
|
- |
| Natural Gas | $38,587 | 6,511 |
MMBtu
|
$5.93 |
| TOTAL YEARLY COSTS | $824,968 | |||
| RECOMMENDED SAVINGS* | $11,338 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $10,834 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,131 | $19,250 |
$4,518
124,829
kWh
|
$613
-
kW-mo/yr
|
|
| 02 | 2.7135: Install occupancy sensors | $1,633 | $944 |
$1,633
45,101
kWh
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,312 | $560 |
$1,156
31,972
kWh
|
$156
-
kW-mo/yr
|
|
| 04 | 2.7446: Utilize sensors controlling roof and wall openings | $533 | $195 |
$533
14,744
kWh
|
- | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $504 | $70 |
$444
12,264
kWh
|
$60
-
kW-mo/yr
|
|
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,225 | $5,350 |
$1,601
44,235
kWh
|
$624
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $11,338 | $26,369 |
$9,885
273,145
kWh
|
$1,453
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $10,834 | $26,299 |
$9,441
260,881
kWh
|
$1,393
-
kW-mo/yr
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs