Assessment Year | 2016 |
---|---|
Principal Product | Metal Parts |
NAICS | 332312: Fabricated Structural Metal Manufacturing |
SIC | 3449: Miscellaneous Structural Metal Work |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
70,800
ft2
|
Annual Production | 1,000,000
units
|
Production Hrs. Annual | 3,640
hrs
|
Location (State) | South Dakota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $63,116 | 1,025,440 |
kWh
|
$0.062 |
Electricity Demand | $50,385 | 5,004 |
kW-mo/yr
|
$10.07 |
Natural Gas | $31,071 | 9,675 |
MMBtu
|
$3.21 |
TOTAL YEARLY COSTS | $144,572 | |||
RECOMMENDED SAVINGS* | $14,432 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,276 | $17,530 |
$5,997
97,972
kWh
|
$3,279
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,337 | $441 |
$1,528
25,009
kWh
|
$809
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $981 | $2,040 |
$981
16,031
kWh
|
- | - | |
04 | 2.7135: Install occupancy sensors | $589 | $1,290 |
$589
9,592
kWh
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $374 | $60 |
$245
4,004
kWh
|
$129
-
kW-mo/yr
|
- | |
06 | 2.7211: Clean and maintain refrigerant condensers and towers | $352 | $60 |
$145
2,363
kWh
|
$207
-
kW-mo/yr
|
- | |
07 | 2.4221: Install compressor air intakes in coolest locations | $281 | $337 |
$183
2,297
kWh
|
$98
-
kW-mo/yr
|
- | |
08 | 2.1213: Direct warmest air to combustion intake | $242 | $200 | - | - |
$242
-
MMBtu
|
|
TOTAL RECOMMENDED | $14,432 | $21,958 |
$9,668
157,268
kWh
|
$4,522
-
kW-mo/yr
|
$242
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs