Assessment Year | 2016 |
---|---|
Principal Product | cereal |
NAICS | 311230: Breakfast Cereal Manufacturing |
SIC | 2043: Cereal Breakfast Foods |
Sales Range | $10 M to 50M |
# of Employees | 125 |
Plant Area |
143,000
ft2
|
Annual Production | 17,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $106,616 | 4,192,500 |
kWh
|
$0.025 |
Electricity Demand | $182,057 | 9,120 |
kW-mo/yr
|
$19.96 |
Natural Gas | $245,108 | 46,672 |
MMBtu
|
$5.25 |
TOTAL YEARLY COSTS | $533,781 | |||
RECOMMENDED SAVINGS* | $64,308 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,381 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $44,271 | $95,210 |
$19,952
788,611
kWh
|
$24,319
-
kW-mo/yr
|
- | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,548 | $500 |
$743
29,386
kWh
|
$805
-
kW-mo/yr
|
- | - | |
03 | 2.4133: Use most efficient type of electric motors | $5,367 | $29,084 |
$2,371
93,717
kWh
|
$2,996
-
kW-mo/yr
|
- | - | |
04 | 2.3212: Optimize plant power factor | $4,037 | $4,835 | - | - | $4,037 | - | |
05 | 2.7135: Install occupancy sensors | $3,284 | $5,488 |
$3,284
129,808
kWh
|
- | - | - | |
06 | 2.2136: Install / repair insulation on steam lines | $2,719 | $5,030 | - | - | - |
$2,719
-
MMBtu
|
|
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,648 | $189 |
$793
31,273
kWh
|
$855
-
kW-mo/yr
|
- | - | |
08 | 2.2511: Insulate bare equipment | $553 | $242 | - | - | - |
$553
-
MMBtu
|
|
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $461 | $35 |
$222
8,760
kWh
|
$239
-
kW-mo/yr
|
- | - | |
10 | 2.4221: Install compressor air intakes in coolest locations | $420 | $398 |
$171
6,829
kWh
|
$249
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $64,308 | $141,011 |
$27,536
1,088,384
kWh
|
$29,463
-
kW-mo/yr
|
$4,037 |
$3,272
-
MMBtu
|
||
TOTAL IMPLEMENTED | $5,381 | $5,496 |
$1,015
40,033
kWh
|
$1,094
-
kW-mo/yr
|
- |
$3,272
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs