Assessment Year | 2015 |
---|---|
Principal Product | Renewable Corn Products |
NAICS | 311221: Wet Corn Milling |
SIC | 2046: Wet Corn Milling |
Sales Range | $1 M to 5M |
# of Employees | 43 |
Plant Area |
100,000
ft2
|
Annual Production | 45,000
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $539,067 | 8,511,320 |
kWh
|
$0.063 |
Electricity Demand | $178,636 | 16,853 |
kW-mo/yr
|
$10.60 |
Electricity Fees | $14,645 | - |
|
- |
Natural Gas | $9,663 | 1,448 |
MMBtu
|
$6.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $20,731 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,514 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,201 | $9,836 |
$9,080
143,490
kWh
|
$2,121
-
kW-mo/yr
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $5,029 | $542 |
$3,906
61,691
kWh
|
$1,123
-
kW-mo/yr
|
- | |
03 | 2.4133: Use most efficient type of electric motors | $2,913 | $11,538 |
$2,369
37,431
kWh
|
$544
-
kW-mo/yr
|
- | |
04 | 2.2691: Shut off cooling if cold outside air will cool process | $590 | $2,620 |
$590
9,312
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $356 | $269 |
$289
4,552
kWh
|
$67
-
kW-mo/yr
|
- | |
06 | 2.2136: Install / repair insulation on steam lines | $338 | $1,008 | - | - |
$338
-
MMBtu
|
|
07 | 2.7135: Install occupancy sensors | $304 | $488 |
$304
4,777
kWh
|
- | - | |
TOTAL RECOMMENDED | $20,731 | $26,301 |
$16,538
261,253
kWh
|
$3,855
-
kW-mo/yr
|
$338
-
MMBtu
|
||
TOTAL IMPLEMENTED | $17,514 | $14,275 |
$13,865
219,045
kWh
|
$3,311
-
kW-mo/yr
|
$338
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs