ITAC Assessment: LE0194
ITAC logo
ITAC Assessment: LE0194
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Steel Wire
NAICS 331222: Steel Wire Drawing
SIC 3315: Steel Wiredrawing and Steel Nails and Spikes
Sales Range $10
M
to 50
M
# of Employees 49
Plant Area 100,000
ft2
Annual Production 24,000
ton
Production Hrs. Annual 6,240
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $262,940 3,887,520
kWh
Electricity Demand $87,250 10,200
kW-mo/yr
Natural Gas $362,237 57,079
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $979,897 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $933,681

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Primary Product Savings
01 2.2314: Replace heat treating oven with more efficient unit $866,040 $200,000 - - $66,040
-
MMBtu
$800,000
02 2.7496: Install partitions to reduce size of conditioned space $59,658 $12,500 - - $59,658
-
MMBtu
-
03 2.7231: Use radiant heater for spot heating $35,941 $5,625 - - $35,941
-
MMBtu
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,915 $2,000 $5,915
86,989
kWh
- - -
05 2.3131: Reschedule plant operations or reduce load to avoid peaks $4,360 $2,500 - $4,360
-
kW-mo/yr
- -
06 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $4,196 $4,000 $4,196
61,714
kWh
- - -
07 2.1233: Analyze flue gas for proper air/fuel ratio $3,787 $750 - - $3,787
-
MMBtu
-
TOTAL RECOMMENDED $979,897 $227,375 $10,111
148,703
kWh
$4,360
-
kW-mo/yr
$165,426
-
MMBtu
$800,000
TOTAL IMPLEMENTED $933,681 $217,250 $4,196
61,714
kWh
- $129,485
-
MMBtu
$800,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs