ITAC Assessment: CO0455
ITAC logo
ITAC Assessment: CO0455
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product particleboard
NAICS
n/a
SIC 2493: Reconstituted Wood Products
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 140,000
ft2
Annual Production 48,000,000
thousand feet
Production Hrs. Annual 8,712
hrs
Location (State) New Mexico

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $721,833 16,961,020
kWh
Electricity Demand $311,769 31,224
kW-mo/yr
Electricity Fees $74,159 -
Natural Gas $198,909 58,141
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $130,400 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Other Liquid (haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings Primary Product Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $41,240 $10,000 n/a - $41,240
-
kW-mo/yr
- - - - - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,020 $220 n/a $4,690
118,992
kWh
$1,890
-
kW-mo/yr
- - - $(-1,560.0) - - -
03 2.7121: Utilize daylight whenever possible in lieu of artificial light $2,640 - n/a $1,400
27,843
kWh
$1,240
-
kW-mo/yr
- - - - - - -
04 2.4133: Use most efficient type of electric motors $430 $440 n/a $310
7,913
kWh
$120
-
kW-mo/yr
- - - - - - -
05 3.8132: Use less toxic and volatile solvent substitutes $39,330 - n/a - - $(-70.0)
-
Tgal
$38,440
-
gal
- - - $960 -
06 3.5314: Use in-process recycling whenever possible $2,180 $3,500 n/a - - - - $280
-
lb
- $1,900 - -
07 4.624: Hire additional personnel to reduce changeout time $39,560 $1,000 n/a - - - - - $(-40,000.0) - - $79,560
TOTAL RECOMMENDED $130,400 $15,160 $6,400
154,748
kWh
$44,490
-
kW-mo/yr
$(-70.0)
-
Tgal
$38,440
-
gal
$280
-
lb
$(-41,560.0) $1,900 $960 $79,560
TOTAL IMPLEMENTED - - - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Other Liquid (haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs