ITAC Assessment: IA0521
ITAC logo
ITAC Assessment: IA0521
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Aluminum Castings
NAICS 331524: Aluminum Foundries (except Die-Casting)
SIC 3365: Aluminum Foundries
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 80,948
ft2
Annual Production 6,200,000
lb
Production Hrs. Annual 6,732
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $427,481 8,939,250
kWh
Electricity Demand $357,903 17,044
kW-mo/yr
Electricity Fees $9,373 -
Natural Gas $302,574 48,999
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $184,803 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $135,666

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $116,438 $25,000 - - $69,525
-
MMBtu
$46,913
-
lb
02 2.2511: Insulate bare equipment $7,861 $500 - - $7,861
-
MMBtu
-
03 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $4,593 $1,750 $2,580
53,856
kWh
$2,013
-
kW-mo/yr
- -
04 2.2414: Use waste heat from hot flue gases to preheat $41,190 $3,600 - - $41,190
-
MMBtu
-
05 2.4221: Install compressor air intakes in coolest locations $6,258 $355 $3,542
73,968
kWh
$2,716
-
kW-mo/yr
- -
06 2.4231: Reduce the pressure of compressed air to the minimum required $3,158 $70 $1,774
37,026
kWh
$1,384
-
kW-mo/yr
- -
07 2.4239: Eliminate or reduce compressed air usage $3,616 $2,313 $219
4,580
kWh
$3,397
-
kW-mo/yr
- -
08 2.7243: Improve air circulation with destratification fans / other methods $1,689 $350 - - $1,689
-
MMBtu
-
TOTAL RECOMMENDED $184,803 $33,938 $8,115
169,430
kWh
$9,510
-
kW-mo/yr
$120,265
-
MMBtu
$46,913
-
lb
TOTAL IMPLEMENTED $135,666 $29,633 $4,573
95,462
kWh
$6,794
-
kW-mo/yr
$77,386
-
MMBtu
$46,913
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs