ITAC Assessment: IA0518
ITAC logo
ITAC Assessment: IA0518
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Food Packaging Equipment
NAICS 333993: Packaging Machinery Manufacturing
SIC 3565: Packaging Machinery
Sales Range $50
M
to 100
M
# of Employees 262
Plant Area 140,000
ft2
Annual Production 1,200
pieces
Production Hrs. Annual 4,368
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $114,067 1,604,000
kWh
Electricity Demand $37,712 4,524
kW-mo/yr
Electricity Fees $5,598 -
Natural Gas $30,528 4,572
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,135 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,209

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,434 $704 $2,598
36,512
kWh
$836
-
kW-mo/yr
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,232 $5,280 $932
13,104
kWh
$300
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $742 $1,050 $561
7,888
kWh
$181
-
kW-mo/yr
-
04 2.4221: Install compressor air intakes in coolest locations $939 $185 $699
9,841
kWh
$240
-
kW-mo/yr
-
05 2.7135: Install occupancy sensors $184 $140 $139
1,957
kWh
$45
-
kW-mo/yr
-
06 2.7135: Install occupancy sensors $149 $210 $149
2,091
kWh
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $2,190 $8,793 $2,190
30,809
kWh
- -
08 2.1131: Repair faulty insulation in furnaces, boilers, etc $462 $80 - - $462
-
MMBtu
09 2.2437: Recover waste heat from equipment $1,803 $2,302 - - $1,803
-
MMBtu
TOTAL RECOMMENDED $11,135 $18,744 $7,268
102,202
kWh
$1,602
-
kW-mo/yr
$2,265
-
MMBtu
TOTAL IMPLEMENTED $10,209 $17,554 $6,568
92,357
kWh
$1,376
-
kW-mo/yr
$2,265
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs