ITAC Assessment: IA0499
ITAC logo
ITAC Assessment: IA0499
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product chemical reagents
NAICS 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing
SIC 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 350
Plant Area 170,000
ft2
Annual Production 100,000
pieces
Production Hrs. Annual 4,940
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $490,046 6,879,600
kWh
Electricity Demand $52,529 12,962
kW-mo/yr
Electricity Fees $17,402 -
Natural Gas $91,680 28,708
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,369 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,768

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.3212: Optimize plant power factor $7,492 $3,371 - - - $7,492
02 2.4221: Install compressor air intakes in coolest locations $1,315 $700 $1,170
16,529
kWh
$145
-
kW-mo/yr
- -
03 2.4239: Eliminate or reduce compressed air usage $521 $800 $521
7,363
kWh
- - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,972 $830 $2,609
36,852
kWh
$363
-
kW-mo/yr
- -
05 2.4231: Reduce the pressure of compressed air to the minimum required $1,513 $210 $1,329
18,772
kWh
$184
-
kW-mo/yr
- -
06 2.4133: Use most efficient type of electric motors $1,445 $4,953 $1,269
17,926
kWh
$176
-
kW-mo/yr
- -
07 2.7135: Install occupancy sensors $1,768 $3,800 $1,768
24,966
kWh
- - -
08 2.2113: Repair or replace steam traps $1,343 $1,425 - - $1,343
-
MMBtu
-
TOTAL RECOMMENDED $18,369 $16,089 $8,666
122,408
kWh
$868
-
kW-mo/yr
$1,343
-
MMBtu
$7,492
TOTAL IMPLEMENTED $1,768 $3,800 $1,768
24,966
kWh
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs