ITAC Assessment: IA0471
ITAC logo
ITAC Assessment: IA0471
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Poultry and Hog Feed
NAICS 311119: Other Animal Food Manufacturing
SIC 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats
Sales Range $50
M
to 100
M
# of Employees 22
Plant Area 50,000
ft2
Annual Production 800,000,000
lb
Production Hrs. Annual 6,864
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $350,581 7,027,200
kWh
Electricity Demand $182,536 18,564
kW-mo/yr
Electricity Fees $404 -
Natural Gas $151,593 30,675
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,909 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,909

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $262 $250 $123
2,464
kWh
$139
-
kW-mo/yr
-
02 2.7135: Install occupancy sensors $979 $1,463 $979
19,615
kWh
- -
03 2.2136: Install / repair insulation on steam lines $1,799 $227 - - $1,799
-
MMBtu
04 2.4224: Upgrade controls on compressors $2,430 $3,832 $1,553
31,133
kWh
$877
-
kW-mo/yr
-
05 2.1243: Use heat from boiler blowdown to preheat boiler feed water $465 $3,000 - - $465
-
MMBtu
06 2.2628: Utilize a less expensive cooling method $1,974 $1,500 $1,974
39,564
kWh
- -
TOTAL RECOMMENDED $7,909 $10,272 $4,629
92,776
kWh
$1,016
-
kW-mo/yr
$2,264
-
MMBtu
TOTAL IMPLEMENTED $7,909 $10,272 $4,629
92,776
kWh
$1,016
-
kW-mo/yr
$2,264
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs