Assessment Year | 2011 |
---|---|
Principal Product | Poultry and Hog Feed |
NAICS | 311119: Other Animal Food Manufacturing |
SIC | 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats |
Sales Range | $50 M to 100M |
# of Employees | 22 |
Plant Area |
50,000
ft2
|
Annual Production | 800,000,000
lb
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $350,581 | 7,027,200 |
kWh
|
$0.050 |
Electricity Demand | $182,536 | 18,564 |
kW-mo/yr
|
$9.83 |
Electricity Fees | $404 | - |
|
- |
Natural Gas | $151,593 | 30,675 |
MMBtu
|
$4.94 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $7,909 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,909 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $262 | $250 |
$123
2,464
kWh
|
$139
-
kW-mo/yr
|
- | |
02 | 2.7135: Install occupancy sensors | $979 | $1,463 |
$979
19,615
kWh
|
- | - | |
03 | 2.2136: Install / repair insulation on steam lines | $1,799 | $227 | - | - |
$1,799
-
MMBtu
|
|
04 | 2.4224: Upgrade controls on compressors | $2,430 | $3,832 |
$1,553
31,133
kWh
|
$877
-
kW-mo/yr
|
- | |
05 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $465 | $3,000 | - | - |
$465
-
MMBtu
|
|
06 | 2.2628: Utilize a less expensive cooling method | $1,974 | $1,500 |
$1,974
39,564
kWh
|
- | - | |
TOTAL RECOMMENDED | $7,909 | $10,272 |
$4,629
92,776
kWh
|
$1,016
-
kW-mo/yr
|
$2,264
-
MMBtu
|
||
TOTAL IMPLEMENTED | $7,909 | $10,272 |
$4,629
92,776
kWh
|
$1,016
-
kW-mo/yr
|
$2,264
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs