ITAC Assessment: SJ0020
ITAC logo
ITAC Assessment: SJ0020
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Wood shavings for ag/pet and industrial wood flour
NAICS 321219: Reconstituted Wood Product Manufacturing
SIC 2493: Reconstituted Wood Products
Sales Range $10
M
to 50
M
# of Employees 34
Plant Area 38,000
ft2
Annual Production 38,000
ton
Production Hrs. Annual 7,488
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $387,750 2,451,284
kWh
Electricity Demand $238,090 5,071
kW-mo/yr
LPG $21,044 659
MMBtu
TOTAL YEARLY COSTS $646,884
RECOMMENDED SAVINGS* $174,023 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings
01 2.9114: Use solar heat to make electricty $140,348 $663,784 $139,104
879,392
kWh
$1,244
-
kW-mo/yr
- -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $23,898 $9,577 $16,195
102,382
kWh
$7,703
-
kW-mo/yr
- -
03 2.7135: Install occupancy sensors $156 $358 $106
671
kWh
$50
-
kW-mo/yr
- -
04 2.7135: Install occupancy sensors $178 $770 $68
432
kWh
$110
-
kW-mo/yr
- -
05 2.4231: Reduce the pressure of compressed air to the minimum required $1,344 - $867
5,483
kWh
$477
-
kW-mo/yr
- -
06 2.7221: Lower temperature during the winter season and vice-versa $2,851 - $221
1,394
kWh
- - $2,630
-
MMBtu
07 2.1332: Convert combustion equipment to burn natural gas $2,380 - - - $(-3,916.0)
-
MMBtu
$6,296
-
MMBtu
08 2.1321: Replace fossil fuel equipment with electrical equipment $2,868 $15,989 $(-1,962.0)
(-12,402)
kWh
- - $4,830
-
MMBtu
TOTAL RECOMMENDED $174,023 $690,478 $154,599
977,352
kWh
$9,584
-
kW-mo/yr
$(-3,916.0)
-
MMBtu
$13,756
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs