ITAC Assessment: IA0465
ITAC logo
ITAC Assessment: IA0465
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Vertical Turbine Pumps
NAICS 333911: Pump and Pumping Equipment Manufacturing
SIC 3561: Pumps and Pumping Equipment
Sales Range $10
M
to 50
M
# of Employees 160
Plant Area 220,000
ft2
Annual Production 8,001
pieces
Production Hrs. Annual 6,552
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $501,288 7,006,800
kWh
Natural Gas $89,211 13,555
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $58,849 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,456 $246 $2,456
37,161
kWh
-
02 2.4221: Install compressor air intakes in coolest locations $1,745 $396 $1,745
24,390
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $3,614 $7,406 $3,614
50,540
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $27,910 $60,314 $27,910
390,624
kWh
-
05 2.7135: Install occupancy sensors $1,368 $616 $1,368
19,140
kWh
-
06 2.7224: Reduce space conditioning during non-working hours $302 $13 - $302
-
MMBtu
07 2.4133: Use most efficient type of electric motors $1,240 $8,646 $1,240
17,306
kWh
-
08 2.7231: Use radiant heater for spot heating $20,214 $48,000 - $20,214
-
MMBtu
TOTAL RECOMMENDED $58,849 $125,637 $38,333
539,161
kWh
$20,516
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs