| Assessment Year | 2011 |
|---|---|
| Principal Product | Hand winches, trailer tongue jacks, and couplers |
| NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
| SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
| Sales Range | $10 M to 50M |
| # of Employees | 180 |
| Plant Area |
185,786
ft2
|
| Annual Production | 1,017,756
pieces
|
| Production Hrs. Annual | 5,329
hrs
|
| Location (State) | Nebraska |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $131,699 | 2,359,560 |
kWh
|
$0.056 |
| Electricity Demand | $49,932 | 6,972 |
kW-mo/yr
|
$7.16 |
| Natural Gas | $46,050 | 8,105 |
MMBtu
|
$5.68 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $25,142 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $25,142 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2135: Repair and eliminate steam leaks | $1,766 | $700 |
$1,007
18,010
kWh
|
$759
-
kW-mo/yr
|
|
| 02 | 2.4221: Install compressor air intakes in coolest locations | $387 | $290 |
$219
3,964
kWh
|
$168
-
kW-mo/yr
|
|
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $380 | $15 |
$217
3,876
kWh
|
$163
-
kW-mo/yr
|
|
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $1,199 | $45 |
$704
11,750
kWh
|
$495
-
kW-mo/yr
|
|
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,295 | $10,281 |
$3,696
61,690
kWh
|
$2,599
-
kW-mo/yr
|
|
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,737 | $33,313 |
$7,477
124,848
kWh
|
$5,260
-
kW-mo/yr
|
|
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,378 | $7,606 |
$1,396
23,298
kWh
|
$982
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $25,142 | $52,250 |
$14,716
247,436
kWh
|
$10,426
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $25,142 | $52,250 |
$14,716
247,436
kWh
|
$10,426
-
kW-mo/yr
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs