Assessment Year | 2011 |
---|---|
Principal Product | Pellet Die and Hammer Mills |
NAICS | 333120: Construction Machinery Manufacturing |
SIC | 3531: Construction Machinery and Equipment |
Sales Range | less than $500 k |
# of Employees | 81 |
Plant Area |
120,000
ft2
|
Annual Production | 1
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $181,575 | 3,624,252 |
kWh
|
$0.050 |
Electricity Demand | $3,236 | 628 |
kW-mo/yr
|
$5.15 |
Natural Gas | $24,037 | 2,916 |
MMBtu
|
$8.24 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,081 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,581 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,522 | $4,244 |
$2,047
40,768
kWh
|
$475
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,099 | $7,498 |
$4,260
84,864
kWh
|
$839
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $802 | $1,695 |
$575
11,457
kWh
|
$227
-
kW-mo/yr
|
- | |
04 | 2.7135: Install occupancy sensors | $282 | $200 |
$282
5,624
kWh
|
- | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $195 | $200 |
$147
2,926
kWh
|
$48
-
kW-mo/yr
|
- | |
06 | 2.4221: Install compressor air intakes in coolest locations | $333 | $200 |
$285
5,684
kWh
|
$48
-
kW-mo/yr
|
- | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $367 | $50 |
$281
5,600
kWh
|
$86
-
kW-mo/yr
|
- | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $575 | $50 |
$495
9,780
kWh
|
$80
-
kW-mo/yr
|
- | |
09 | 2.4133: Use most efficient type of electric motors | $1,176 | $3,670 |
$1,019
20,305
kWh
|
$157
-
kW-mo/yr
|
- | |
10 | 2.2437: Recover waste heat from equipment | $730 | $200 | - | - |
$730
-
MMBtu
|
|
TOTAL RECOMMENDED | $12,081 | $18,007 |
$9,391
187,008
kWh
|
$1,960
-
kW-mo/yr
|
$730
-
MMBtu
|
||
TOTAL IMPLEMENTED | $10,581 | $17,557 |
$8,749
174,302
kWh
|
$1,832
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs