Assessment Year | 2010 |
---|---|
Principal Product | Dairy, Nonfat dry milk |
NAICS | 311511: Fluid Milk Manufacturing |
SIC | 2023: Dry, Condensed, and Evaporated Dairy Products |
Sales Range | $50 M to 100M |
# of Employees | 47 |
Plant Area |
78,000
ft2
|
Annual Production | 500,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $457,883 | 6,903,000 |
kWh
|
$0.066 |
Electricity Demand | $83,938 | 11,587 |
kW-mo/yr
|
$7.24 |
Natural Gas | $1,012,258 | 190,031 |
MMBtu
|
$5.33 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $72,227 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $38,076 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,460 | $3,923 |
$3,513
52,951
kWh
|
$947
-
kW-mo/yr
|
- | |
02 | 2.7135: Install occupancy sensors | $1,643 | $1,978 |
$1,643
24,760
kWh
|
- | - | |
03 | 2.2691: Shut off cooling if cold outside air will cool process | $21,406 | $10,000 |
$21,406
322,392
kWh
|
- | - | |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $23,761 | $1,000 | - | - |
$23,761
-
MMBtu
|
|
05 | 2.1213: Direct warmest air to combustion intake | $7,611 | $1,500 | - | - |
$7,611
-
MMBtu
|
|
06 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $2,057 | $1,500 | - | - |
$2,057
-
MMBtu
|
|
07 | 2.2135: Repair and eliminate steam leaks | $700 | $1,000 | - | - |
$700
-
MMBtu
|
|
08 | 2.4133: Use most efficient type of electric motors | $3,899 | $329 |
$3,349
50,436
kWh
|
$550
-
kW-mo/yr
|
- | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,256 | $500 |
$4,572
68,853
kWh
|
$684
-
kW-mo/yr
|
- | |
10 | 2.4221: Install compressor air intakes in coolest locations | $1,434 | $450 |
$1,248
18,746
kWh
|
$186
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $72,227 | $22,180 |
$35,731
538,138
kWh
|
$2,367
-
kW-mo/yr
|
$34,129
-
MMBtu
|
||
TOTAL IMPLEMENTED | $38,076 | $6,752 |
$11,434
172,240
kWh
|
$2,181
-
kW-mo/yr
|
$24,461
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs