Assessment Year | 2010 |
---|---|
Principal Product | Electronic Display Systems |
NAICS | 334419: Other Electronic Component Manufacturing |
SIC | 3993: Signs and Advertising Specialties |
Sales Range | greater than $500 M |
# of Employees | 2,400 |
Plant Area |
740,000
ft2
|
Annual Production | 200,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | South Dakota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $510,863 | 15,374,116 |
kWh
|
$0.033 |
Electricity Demand | $367,930 | 33,444 |
kW-mo/yr
|
$11.00 |
Electricity Fees | $52,729 | - |
|
- |
Natural Gas | $47,691 | 6,029 |
MMBtu
|
$7.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,188 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,607 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,680 | $5,214 |
$1,637
49,296
kWh
|
$1,043
-
kW-mo/yr
|
- | |
02 | 2.7135: Install occupancy sensors | $1,365 | $1,560 |
$1,365
41,124
kWh
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,363 | $20 |
$829
24,960
kWh
|
$534
-
kW-mo/yr
|
- | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $218 | $20 |
$86
2,600
kWh
|
$132
-
kW-mo/yr
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,229 | $300 |
$1,972
59,405
kWh
|
$1,257
-
kW-mo/yr
|
- | |
06 | 2.2437: Recover waste heat from equipment | $980 | $400 | - | - |
$980
-
MMBtu
|
|
07 | 2.4221: Install compressor air intakes in coolest locations | $1,152 | $300 |
$713
21,481
kWh
|
$439
-
kW-mo/yr
|
- | |
08 | 2.4221: Install compressor air intakes in coolest locations | $201 | $150 |
$74
2,281
kWh
|
$127
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $11,188 | $7,964 |
$6,676
201,147
kWh
|
$3,532
-
kW-mo/yr
|
$980
-
MMBtu
|
||
TOTAL IMPLEMENTED | $9,607 | $7,924 |
$5,761
173,587
kWh
|
$2,866
-
kW-mo/yr
|
$980
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs