ITAC Assessment: IA0446
ITAC logo
ITAC Assessment: IA0446
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Composite pressure vessels
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range less than $500
k
# of Employees 135
Plant Area 201,000
ft2
Annual Production 13,000
units
Production Hrs. Annual 6,000
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $171,045 7,629,500
kWh
Electricity Demand $262,756 16,392
kW-mo/yr
Natural Gas $478,375 43,621
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $232,741 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $136,226

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Consumption Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $6,768 $5,819 $2,705
124,080
kWh
$4,063
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $36,189 $29,591 $14,555
667,800
kWh
$21,634
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $17,951 $12,486 $7,221
331,200
kWh
$10,730
-
kW-mo/yr
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $24,368 $32,570 $6,833
313,628
kWh
$17,535
-
kW-mo/yr
- -
05 2.7135: Install occupancy sensors $374 $876 $374
17,140
kWh
- - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,146 $268 $1,708
78,246
kWh
$2,438
-
kW-mo/yr
- -
07 2.2514: Cover open tanks $26,317 $20,000 - - $26,317
-
MMBtu
-
08 2.4323: Use optimum size and capacity equipment $23,136 $15,000 - - $23,136
-
MMBtu
-
09 2.2511: Insulate bare equipment $4,474 $3,180 - - $4,474
-
MMBtu
-
10 2.4239: Eliminate or reduce compressed air usage $4,136 $740 $4,136
189,742
kWh
- - -
11 2.4239: Eliminate or reduce compressed air usage $10,917 $1,860 $5,412
248,258
kWh
$5,505
-
kW-mo/yr
- -
12 2.4231: Reduce the pressure of compressed air to the minimum required $5,241 $15 $2,597
119,136
kWh
$2,644
-
kW-mo/yr
- -
13 2.2437: Recover waste heat from equipment $21,403 $1,860 - - $21,403
-
MMBtu
-
14 2.1243: Use heat from boiler blowdown to preheat boiler feed water $505 $1,000 - - $505
-
MMBtu
-
15 2.1213: Direct warmest air to combustion intake $333 $213 - - $333
-
MMBtu
-
16 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $16,258 $40,000 - - $16,258
-
MMBtu
-
17 2.2136: Install / repair insulation on steam lines $1,399 $1,461 $357
16,364
kWh
- $1,042
-
MMBtu
-
18 2.2164: Turn off steam tracing during mild weather $957 $260 $244
11,193
kWh
- $713
-
MMBtu
-
19 2.7229: Air condition only space necessary $1,847 $3,725 $1,847
84,744
kWh
- - -
20 2.7243: Improve air circulation with destratification fans / other methods $943 $2,600 - - $943
-
MMBtu
-
21 3.4154: Eliminate leaks in water lines and valves $2,298 $115 - - - $2,298
-
Tgal
22 2.6231: Utilize controls to operate equipment only when needed $19,469 $15,000 - - $19,469
-
MMBtu
-
23 2.7224: Reduce space conditioning during non-working hours $3,312 $2,060 $741
33,980
kWh
- $2,571
-
MMBtu
-
TOTAL RECOMMENDED $232,741 $190,699 $48,730
2,235,511
kWh
$64,549
-
kW-mo/yr
$117,164
-
MMBtu
$2,298
-
Tgal
TOTAL IMPLEMENTED $136,226 $139,785 $38,517
1,767,009
kWh
$56,400
-
kW-mo/yr
$39,011
-
MMBtu
$2,298
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs