ITAC Assessment: IA0409
ITAC logo
ITAC Assessment: IA0409
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Fabricated Steel
NAICS 423510: Metal Service Centers and Other Metal Merchant Wholesalers
SIC 5051: Metals Service Centers and Offices
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 90,000
ft2
Annual Production 40,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $47,637 1,408,800
kWh
Electricity Demand $13,770 4,035
kW-mo/yr
Natural Gas $32,177 3,474
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,416 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,242

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $579 $1,391 $485
14,352
kWh
$94
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,762 $12,621 $3,986
117,936
kWh
$776
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,004 $3,247 $651
19,292
kWh
$353
-
kW-mo/yr
-
04 2.7135: Install occupancy sensors $174 $462 $174
4,341
kWh
- -
05 2.4133: Use most efficient type of electric motors $125 $38 $104
3,081
kWh
$21
-
kW-mo/yr
-
06 2.4231: Reduce the pressure of compressed air to the minimum required $1,312 $25 $1,107
32,760
kWh
$205
-
kW-mo/yr
-
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,664 $440 $1,393
41,207
kWh
$271
-
kW-mo/yr
-
08 2.7261: Install timers and/or thermostats $1,796 $450 - - $1,796
-
MMBtu
TOTAL RECOMMENDED $11,416 $18,674 $7,900
232,969
kWh
$1,720
-
kW-mo/yr
$1,796
-
MMBtu
TOTAL IMPLEMENTED $11,242 $18,212 $7,726
228,628
kWh
$1,720
-
kW-mo/yr
$1,796
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs