Assessment Year | 2007 |
---|---|
Principal Product | Refrigerator components |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 54 |
Plant Area |
92,000
ft2
|
Annual Production | 8,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $338,556 | 8,235,216 |
kWh
|
$0.041 |
Electricity Demand | $214,620 | 17,064 |
kW-mo/yr
|
$12.58 |
Natural Gas | $21,074 | 1,886 |
MMBtu
|
$11.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $41,221 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $26,554 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $1,619 | $100 |
$1,069
26,992
kWh
|
$550
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,837 | $500 |
$1,843
46,550
kWh
|
$994
-
kW-mo/yr
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,667 | $19,110 |
$9,528
240,615
kWh
|
$5,139
-
kW-mo/yr
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,224 | $2,791 |
$741
18,665
kWh
|
$483
-
kW-mo/yr
|
- | - | |
05 | 2.7124: Make a practice of turning off lights when not needed | $3,324 | $238 |
$2,160
54,538
kWh
|
$1,164
-
kW-mo/yr
|
- | - | |
06 | 2.3212: Optimize plant power factor | $4,587 | $300 | - | - | $4,587 | - | |
07 | 2.4133: Use most efficient type of electric motors | $2,458 | $125 |
$1,597
40,316
kWh
|
$861
-
kW-mo/yr
|
- | - | |
08 | 2.2531: Re-size charging openings or add movable cover or door | $2,837 | $800 | - | - | - |
$2,837
-
MMBtu
|
|
09 | 2.7314: Reduce ventilation air | $7,668 | $4,500 | - | - | - |
$7,668
-
MMBtu
|
|
TOTAL RECOMMENDED | $41,221 | $28,464 |
$16,938
427,676
kWh
|
$9,191
-
kW-mo/yr
|
$4,587 |
$10,505
-
MMBtu
|
||
TOTAL IMPLEMENTED | $26,554 | $9,354 |
$7,410
187,061
kWh
|
$4,052
-
kW-mo/yr
|
$4,587 |
$10,505
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs