Assessment Year | 2007 |
---|---|
Principal Product | Sugar cones |
NAICS | 311821: Cookie and Cracker Manufacturing |
SIC | 2052: Cookies and Crackers |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
75,000
ft2
|
Annual Production | 450,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $55,094 | 2,210,900 |
kWh
|
$0.025 |
Electricity Demand | $40,822 | 4,608 |
kW-mo/yr
|
$8.86 |
Electricity Fees | $2,265 | - |
|
- |
Natural Gas | $362,821 | 37,108 |
MMBtu
|
$9.78 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,101 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,153 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $984 | $750 | - | - |
$984
-
MMBtu
|
|
02 | 2.4221: Install compressor air intakes in coolest locations | $948 | $100 |
$561
22,447
kWh
|
$387
-
kW-mo/yr
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,132 | $25 |
$1,269
50,544
kWh
|
$863
-
kW-mo/yr
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $855 | $400 |
$508
20,280
kWh
|
$347
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,814 | $12,468 |
$3,461
137,904
kWh
|
$2,353
-
kW-mo/yr
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,368 | $14,768 |
$2,600
103,584
kWh
|
$1,768
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $15,101 | $28,511 |
$8,399
334,759
kWh
|
$5,718
-
kW-mo/yr
|
$984
-
MMBtu
|
||
TOTAL IMPLEMENTED | $14,153 | $28,411 |
$7,838
312,312
kWh
|
$5,331
-
kW-mo/yr
|
$984
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs