ITAC Assessment: IA0402
ITAC logo
ITAC Assessment: IA0402
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Handles and Latches
NAICS 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 300
Plant Area 130,000
ft2
Annual Production 5,500,000
pieces
Production Hrs. Annual 8,736
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $334,933 5,905,800
kWh
Electricity Demand $22,003 12,372
kW-mo/yr
Natural Gas $217,712 21,301
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $101,084 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $98,813

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,419 $512 $2,322
41,057
kWh
$97
-
kW-mo/yr
-
02 2.4221: Install compressor air intakes in coolest locations $5,179 $1,720 $4,964
87,852
kWh
$215
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $36,343 $44,874 $34,837
616,584
kWh
$1,506
-
kW-mo/yr
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $993 $6,575 $841
14,893
kWh
$152
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $2,589 $7,711 $2,483
43,994
kWh
$106
-
kW-mo/yr
-
06 2.4133: Use most efficient type of electric motors $116 $158 $110
1,950
kWh
$6
-
kW-mo/yr
-
07 2.2514: Cover open tanks $6,793 $599 - - $6,793
-
MMBtu
08 2.2442: Preheat combustion air with waste heat $229 $137 - - $229
-
MMBtu
09 2.1134: Eliminate leaks in combustible gas lines $765 $667 - - $765
-
MMBtu
10 2.2511: Insulate bare equipment $2,271 $3,989 - - $2,271
-
MMBtu
11 2.7314: Reduce ventilation air $38,317 $10,141 - - $38,317
-
MMBtu
12 2.2614: Use cooling tower or economizer to replace chiller cooling $5,070 $3,770 $5,070
89,742
kWh
- -
TOTAL RECOMMENDED $101,084 $80,853 $50,627
896,072
kWh
$2,082
-
kW-mo/yr
$48,375
-
MMBtu
TOTAL IMPLEMENTED $98,813 $76,864 $50,627
896,072
kWh
$2,082
-
kW-mo/yr
$46,104
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs