Assessment Year | 2006 |
---|---|
Principal Product | Heavy-duty oil filters |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $100 M to 500M |
# of Employees | 500 |
Plant Area |
580,000
ft2
|
Annual Production | 30,000,000
pieces
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $594,135 | 20,060,581 |
kWh
|
$0.030 |
Electricity Demand | $286,668 | 41,556 |
kW-mo/yr
|
$6.90 |
Electricity Fees | $615 | - |
|
- |
Natural Gas | $323,984 | 30,759 |
MMBtu
|
$10.53 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $67,613 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $65,063 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,713 | $40,358 |
$9,481
330,275
kWh
|
$4,232
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $28,511 | $66,554 |
$20,097
700,239
kWh
|
$8,414
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,749 | $7,994 |
$3,922
136,660
kWh
|
$1,827
-
kW-mo/yr
|
- | |
04 | 2.7135: Install occupancy sensors | $1,893 | $3,850 |
$1,893
66,031
kWh
|
- | - | |
05 | 2.1213: Direct warmest air to combustion intake | $2,308 | $735 | - | - |
$2,308
-
MMBtu
|
|
06 | 2.4221: Install compressor air intakes in coolest locations | $2,268 | $2,268 |
$1,670
58,198
kWh
|
$598
-
kW-mo/yr
|
- | |
07 | 2.2437: Recover waste heat from equipment | $12,514 | $1,650 | - | - |
$12,514
-
MMBtu
|
|
08 | 2.4322: Use or replace with energy efficient substitutes | $657 | $1,300 |
$471
6,416
kWh
|
$186
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $67,613 | $124,709 |
$37,534
1,297,819
kWh
|
$15,257
-
kW-mo/yr
|
$14,822
-
MMBtu
|
||
TOTAL IMPLEMENTED | $65,063 | $119,559 |
$35,170
1,225,372
kWh
|
$15,071
-
kW-mo/yr
|
$14,822
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs