ITAC Assessment: IA0392
ITAC logo
ITAC Assessment: IA0392
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Heavy-duty oil filters
NAICS 336390: Other Motor Vehicle Parts Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $100
M
to 500
M
# of Employees 500
Plant Area 580,000
ft2
Annual Production 30,000,000
pieces
Production Hrs. Annual 7,200
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $594,135 20,060,581
kWh
Electricity Demand $286,668 41,556
kW-mo/yr
Electricity Fees $615 -
Natural Gas $323,984 30,759
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $67,613 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $65,063

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $13,713 $40,358 $9,481
330,275
kWh
$4,232
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $28,511 $66,554 $20,097
700,239
kWh
$8,414
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $5,749 $7,994 $3,922
136,660
kWh
$1,827
-
kW-mo/yr
-
04 2.7135: Install occupancy sensors $1,893 $3,850 $1,893
66,031
kWh
- -
05 2.1213: Direct warmest air to combustion intake $2,308 $735 - - $2,308
-
MMBtu
06 2.4221: Install compressor air intakes in coolest locations $2,268 $2,268 $1,670
58,198
kWh
$598
-
kW-mo/yr
-
07 2.2437: Recover waste heat from equipment $12,514 $1,650 - - $12,514
-
MMBtu
08 2.4322: Use or replace with energy efficient substitutes $657 $1,300 $471
6,416
kWh
$186
-
kW-mo/yr
-
TOTAL RECOMMENDED $67,613 $124,709 $37,534
1,297,819
kWh
$15,257
-
kW-mo/yr
$14,822
-
MMBtu
TOTAL IMPLEMENTED $65,063 $119,559 $35,170
1,225,372
kWh
$15,071
-
kW-mo/yr
$14,822
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs