ITAC Assessment: IA0381
ITAC logo
ITAC Assessment: IA0381
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Corrugated Boxes
NAICS 322211: Corrugated and Solid Fiber Box Manufacturing
SIC 2631: Paperboard Mills
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 275,000
ft2
Annual Production 70,700,000
lb
Production Hrs. Annual 6,360
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $274,628 6,734,100
kWh
Electricity Demand $120,270 1,374
kW-mo/yr
Electricity Fees $5,453 -
Natural Gas $548,557 70,595
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $247,846 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $36,968

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,587 $500 $1,185
29,256
kWh
$402
-
kW-mo/yr
-
02 2.4221: Install compressor air intakes in coolest locations $8,477 $416 $6,409
158,897
kWh
$2,068
-
kW-mo/yr
-
03 2.4231: Reduce the pressure of compressed air to the minimum required $3,656 $25 $2,730
67,416
kWh
$926
-
kW-mo/yr
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $593 $877 $429
10,540
kWh
$164
-
kW-mo/yr
-
05 2.7135: Install occupancy sensors $1,196 $300 $1,196
29,527
kWh
- -
06 2.7122: Disconnect ballasts $6,622 $375 $4,945
122,112
kWh
$1,677
-
kW-mo/yr
-
07 2.4133: Use most efficient type of electric motors $1,382 $458 $1,032
25,491
kWh
$350
-
kW-mo/yr
-
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,966 $345 $2,215
54,696
kWh
$751
-
kW-mo/yr
-
09 2.4131: Size electric motors for peak operating efficiency $50,899 $10,400 $24,329
600,726
kWh
$8,247
-
kW-mo/yr
$18,323
-
MMBtu
10 2.6218: Turn off equipment when not in use $20,975 $250 $9,730
240,240
kWh
- $11,245
-
MMBtu
11 2.7221: Lower temperature during the winter season and vice-versa $1,907 $425 - - $1,907
-
MMBtu
12 2.7221: Lower temperature during the winter season and vice-versa $4,143 $2,410 - - $4,143
-
MMBtu
13 2.2437: Recover waste heat from equipment $9,399 $730 - - $9,399
-
MMBtu
14 2.2437: Recover waste heat from equipment $6,174 $4,244 - - $6,174
-
MMBtu
15 2.2437: Recover waste heat from equipment $69,963 $111,000 - - $69,963
-
MMBtu
16 2.1133: Adjust burners for efficient operation $6,473 $1,000 - - $6,473
-
MMBtu
17 2.2414: Use waste heat from hot flue gases to preheat $44,160 $18,000 - - $44,160
-
MMBtu
18 2.1213: Direct warmest air to combustion intake $2,512 $170 - - $2,512
-
MMBtu
19 2.6212: Turn off equipment during breaks, reduce operating time $366 $50 - - $366
-
MMBtu
20 2.2135: Repair and eliminate steam leaks $252 $600 - - $252
-
MMBtu
21 2.6218: Turn off equipment when not in use $4,144 $1,925 $4,144
102,375
kWh
- -
TOTAL RECOMMENDED $247,846 $154,500 $58,344
1,441,276
kWh
$14,585
-
kW-mo/yr
$174,917
-
MMBtu
TOTAL IMPLEMENTED $36,968 $5,960 $17,716
437,429
kWh
$916
-
kW-mo/yr
$18,336
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs