Assessment Year | 2004 |
---|---|
Principal Product | processed beef |
NAICS | 311611: Animal (except Poultry) Slaughtering |
SIC | 2011: Meat Packing Plants |
Sales Range | $50 M to 100M |
# of Employees | 125 |
Plant Area |
43,000
ft2
|
Annual Production | 83,200
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $131,004 | 3,858,000 |
kWh
|
$0.034 |
Electricity Demand | $67,299 | 8,880 |
kW-mo/yr
|
$7.58 |
Natural Gas | $204,854 | 29,400 |
MMBtu
|
$6.97 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,580 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2427: Use waste heat from hot flue gases to preheat incoming fluids | $6,831 | $13,500 | - | - |
$6,831
-
MMBtu
|
|
02 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $1,161 | $2,300 | - | - |
$1,161
-
MMBtu
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,472 | $254 |
$848
25,082
kWh
|
$624
-
kW-mo/yr
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $997 | $166 |
$582
17,113
kWh
|
$415
-
kW-mo/yr
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $413 | $25 |
$238
7,020
kWh
|
$175
-
kW-mo/yr
|
- | |
06 | 2.2437: Recover waste heat from equipment | $913 | $857 | - | - |
$913
-
MMBtu
|
|
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,449 | $7,025 |
$1,412
41,652
kWh
|
$1,037
-
kW-mo/yr
|
- | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,027 | $198 |
$696
20,545
kWh
|
$331
-
kW-mo/yr
|
- | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,065 | $4,616 |
$1,228
36,300
kWh
|
$837
-
kW-mo/yr
|
- | |
10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $252 | $630 |
$181
7,972
kWh
|
$71
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $17,580 | $29,571 |
$5,185
155,684
kWh
|
$3,490
-
kW-mo/yr
|
$8,905
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs