ITAC Assessment: IA0332
ITAC logo
ITAC Assessment: IA0332
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Spices
NAICS 311942: Spice and Extract Manufacturing
SIC 2099: Food Preparations, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 500
Plant Area 725,000
ft2
Annual Production 148,000,000
pieces
Production Hrs. Annual 3,120
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $498,112 17,228,248
kWh
Electricity Demand $182,982 32,172
kW-mo/yr
Electricity Fees $10,673 -
Natural Gas $147,617 21,689
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $57,784 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $53,325

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $1,039 $44 $321
16,536
kWh
$718
-
kW-mo/yr
-
02 2.4221: Install compressor air intakes in coolest locations $3,420 $544 $955
49,249
kWh
$2,465
-
kW-mo/yr
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,880 $277 $2,126
109,607
kWh
$4,754
-
kW-mo/yr
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,053 $8,284 $926
47,754
kWh
$2,127
-
kW-mo/yr
-
05 2.4133: Use most efficient type of electric motors $48 $67 $27
1,417
kWh
$21
-
kW-mo/yr
-
06 3.5313: Increase amount of waste recovered for resale $43,344 $11,000 - - $43,344
TOTAL RECOMMENDED $57,784 $20,216 $4,355
224,563
kWh
$10,085
-
kW-mo/yr
$43,344
TOTAL IMPLEMENTED $53,325 $19,628 $3,079
158,778
kWh
$6,902
-
kW-mo/yr
$43,344
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs