Assessment Year | 2003 |
---|---|
Principal Product | Kiln-dried hardwoods, hardwood floorings |
NAICS | 321918: Other Millwork (including Flooring) |
SIC | 2426: Hardwood Dimension and Flooring Mills |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
200,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 3,500
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $62,267 | 2,310,303 |
kWh
|
$0.027 |
Electricity Demand | $88,523 | 10,932 |
kW-mo/yr
|
$8.10 |
Natural Gas | $4,585 | 743 |
MMBtu
|
$6.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,816 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,996 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,364 | $157 |
$722
26,460
kWh
|
$642
-
kW-mo/yr
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $936 | $446 |
$497
18,197
kWh
|
$439
-
kW-mo/yr
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $572 | $712 |
$303
11,095
kWh
|
$269
-
kW-mo/yr
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $632 | $124 |
$390
14,271
kWh
|
$242
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,661 | $6,189 |
$1,387
50,812
kWh
|
$1,274
-
kW-mo/yr
|
- | |
06 | 2.3212: Optimize plant power factor | $11,651 | $20,000 | - | - | $11,651 | |
TOTAL RECOMMENDED | $17,816 | $27,628 |
$3,299
120,835
kWh
|
$2,866
-
kW-mo/yr
|
$11,651 | ||
TOTAL IMPLEMENTED | $1,996 | $281 |
$1,112
40,731
kWh
|
$884
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs