ITAC Assessment: IA0323
ITAC logo
ITAC Assessment: IA0323
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product custom metal fabrications
NAICS 331318: Other Aluminum Rolling, Drawing, and Extruding
SIC 3491: Industrial Valves
Sales Range $10
M
to 50
M
# of Employees 265
Plant Area 305,000
ft2
Annual Production 4,340
ton
Production Hrs. Annual 8,760
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $142,077 4,273,996
kWh
Electricity Demand $88,140 12,816
kW-mo/yr
Natural Gas $91,845 22,179
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,617 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,073

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,618 $1,298 $2,169
65,519
kWh
$449
-
kW-mo/yr
02 2.4221: Install compressor air intakes in coolest locations $1,258 $304 $991
30,073
kWh
$267
-
kW-mo/yr
03 2.4224: Upgrade controls on compressors $4,635 $2,000 $3,096
93,548
kWh
$1,539
-
kW-mo/yr
04 2.7142: Utilize higher efficiency lamps and/or ballasts $748 $737 $596
18,034
kWh
$152
-
kW-mo/yr
05 2.7142: Utilize higher efficiency lamps and/or ballasts $4,455 $8,642 $3,236
97,760
kWh
$1,219
-
kW-mo/yr
06 2.7135: Install occupancy sensors $903 $1,639 $903
27,257
kWh
-
TOTAL RECOMMENDED $14,617 $14,620 $10,991
332,191
kWh
$3,626
-
kW-mo/yr
TOTAL IMPLEMENTED $7,073 $9,940 $5,405
163,279
kWh
$1,668
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs