ITAC Assessment: CO0696
ITAC logo
ITAC Assessment: CO0696
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Pharmaceuticals
NAICS 325414: Biological Product (except Diagnostic) Manufacturing
SIC 2836: Biological Products, Except Diagnostic Substances
Sales Range $10
M
to 50
M
# of Employees 40
Plant Area 19,100
ft2
Annual Production 190,000
pieces
Production Hrs. Annual 2,600
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $75,464 1,672,600
kWh
Electricity Demand $78,354 3,564
kW-mo/yr
Electricity Fees $1,260 -
Natural Gas $59,601 8,792
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,250 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,450

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system $9,930 $22,200 $1,890
40,800
kWh
$8,040
-
kW-mo/yr
- - - -
02 2.8121: Apply for tax-free status for energy purchases $4,140 $500 - - - - $4,140 -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,870 $6,360 $770
16,600
kWh
$840
-
kW-mo/yr
- $90 - $170
04 2.2136: Install / repair insulation on steam lines $310 $480 - - $310
-
MMBtu
- - -
TOTAL RECOMMENDED $16,250 $29,540 $2,660
57,400
kWh
$8,880
-
kW-mo/yr
$310
-
MMBtu
$90 $4,140 $170
TOTAL IMPLEMENTED $4,450 $980 - - $310
-
MMBtu
- $4,140 -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs