| Assessment Year | 2014 |
|---|---|
| Principal Product | Pharmaceuticals |
| NAICS | 325414: Biological Product (except Diagnostic) Manufacturing |
| SIC | 2836: Biological Products, Except Diagnostic Substances |
| Sales Range | $10 M to 50M |
| # of Employees | 40 |
| Plant Area |
19,100
ft2
|
| Annual Production | 190,000
pieces
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $75,464 | 1,672,600 |
kWh
|
$0.045 |
| Electricity Demand | $78,354 | 3,564 |
kW-mo/yr
|
$21.98 |
| Electricity Fees | $1,260 | - |
|
- |
| Natural Gas | $59,601 | 8,792 |
MMBtu
|
$6.78 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $16,250 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,450 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system | $9,930 | $22,200 |
$1,890
40,800
kWh
|
$8,040
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.8121: Apply for tax-free status for energy purchases | $4,140 | $500 | - | - | - | - | $4,140 | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,870 | $6,360 |
$770
16,600
kWh
|
$840
-
kW-mo/yr
|
- | $90 | - | $170 | |
| 04 | 2.2136: Install / repair insulation on steam lines | $310 | $480 | - | - |
$310
-
MMBtu
|
- | - | - | |
| TOTAL RECOMMENDED | $16,250 | $29,540 |
$2,660
57,400
kWh
|
$8,880
-
kW-mo/yr
|
$310
-
MMBtu
|
$90 | $4,140 | $170 | ||
| TOTAL IMPLEMENTED | $4,450 | $980 | - | - |
$310
-
MMBtu
|
- | $4,140 | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs