Assessment Year | 2003 |
---|---|
Principal Product | pressure sensitive labels |
NAICS | 322220: Paper Bag and Coated and Treated Paper Manufacturing |
SIC | 2672: Coated and Laminated Paper, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 325 |
Plant Area |
155,000
ft2
|
Annual Production | 52,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $147,488 | 6,197,100 |
kWh
|
$0.024 |
Electricity Demand | $128,772 | 12,924 |
kW-mo/yr
|
$9.96 |
Natural Gas | $15,095 | 2,849 |
MMBtu
|
$5.30 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $53,857 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,875 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $572 | $69 |
$332
14,226
kWh
|
$240
-
kW-mo/yr
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $701 | $25 |
$409
17,472
kWh
|
$292
-
kW-mo/yr
|
- | |
03 | 2.4226: Use / purchase optimum sized compressor | $4,583 | $3,100 |
$2,673
114,192
kWh
|
$1,910
-
kW-mo/yr
|
- | |
04 | 2.4133: Use most efficient type of electric motors | $370 | $202 |
$216
9,229
kWh
|
$154
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,933 | $1,440 |
$1,127
48,167
kWh
|
$806
-
kW-mo/yr
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,575 | $5,663 |
$918
39,237
kWh
|
$657
-
kW-mo/yr
|
- | |
07 | 2.7135: Install occupancy sensors | $203 | $532 |
$203
8,715
kWh
|
- | - | |
08 | 3.5217: Reuse / recycle/ sell paper products | $43,920 | $320 | - | - |
$43,920
-
lb
|
|
TOTAL RECOMMENDED | $53,857 | $11,351 |
$5,878
251,238
kWh
|
$4,059
-
kW-mo/yr
|
$43,920
-
lb
|
||
TOTAL IMPLEMENTED | $2,875 | $1,711 |
$1,675
71,622
kWh
|
$1,200
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs