Assessment Year | 2002 |
---|---|
Principal Product | injection and blow molded plastic parts |
NAICS |
n/a
|
SIC | 3080: |
Sales Range | $5 M to 10M |
# of Employees | 95 |
Plant Area |
70,000
ft2
|
Annual Production | 3,900,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $183,093 | 5,125,598 |
kWh
|
$0.036 |
Electricity Demand | $86,539 | 12,552 |
kW-mo/yr
|
$6.89 |
Natural Gas | $16,124 | 3,029 |
MMBtu
|
$5.32 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $34,727 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,620 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,148 | $409 |
$1,604
44,928
kWh
|
$544
-
kW-mo/yr
|
- | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $418 | $25 |
$312
8,736
kWh
|
$106
-
kW-mo/yr
|
- | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $1,472 | $253 |
$1,107
30,937
kWh
|
$365
-
kW-mo/yr
|
- | - | |
04 | 2.4133: Use most efficient type of electric motors | $4,148 | - |
$3,099
86,796
kWh
|
$1,049
-
kW-mo/yr
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,479 | - |
$1,094
30,654
kWh
|
$385
-
kW-mo/yr
|
- | - | |
06 | 2.7135: Install occupancy sensors | $686 | $1,131 |
$686
19,220
kWh
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,705 | $7,590 |
$1,814
50,813
kWh
|
$891
-
kW-mo/yr
|
- | - | |
08 | 2.4239: Eliminate or reduce compressed air usage | $1,520 | - |
$714
19,993
kWh
|
$806
-
kW-mo/yr
|
- | - | |
09 | 4.322: Eliminate old stock and modify inventory control | $13,000 | $17,850 | - | - | $13,000 | - | |
10 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $4,038 | $10,900 | - | - | - | $4,038 | |
11 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $3,113 | $3,750 | - | - | - | $3,113 | |
TOTAL RECOMMENDED | $34,727 | $41,908 |
$10,430
292,077
kWh
|
$4,146
-
kW-mo/yr
|
$13,000 | $7,151 | ||
TOTAL IMPLEMENTED | $16,620 | $18,512 |
$2,711
75,865
kWh
|
$909
-
kW-mo/yr
|
$13,000 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs