Assessment Year | 1998 |
---|---|
Principal Product | Corrugated containers |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 157 |
Plant Area |
138,400
ft2
|
Annual Production | 7,200,000
thousand feet
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | South Dakota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $136,935 | 4,606,389 |
kWh
|
$0.030 |
Electricity Demand | $76,079 | 9,948 |
kW-mo/yr
|
$7.65 |
Electricity Fees | $12,973 | - |
|
- |
Natural Gas | $144,753 | 104,954 |
MMBtu
|
$1.38 |
Fuel Oil #2 | $15,952 | 2,980 |
MMBtu
|
$5.35 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,088 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,725 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,447 | $21,490 |
$3,868
128,957
kWh
|
$1,579
-
kW-mo/yr
|
- | - | - | |
02 | 2.3137: Use power during off-peak periods | $3,019 | $1,375 | - |
$3,019
-
kW-mo/yr
|
- | - | - | |
03 | 2.2437: Recover waste heat from equipment | $12,228 | $12,710 |
$(-1,651.0)
(-55,100)
kWh
|
$(-652.0)
-
kW-mo/yr
|
$14,531
-
MMBtu
|
- | - | |
04 | 2.2437: Recover waste heat from equipment | $775 | $680 | - | - |
$775
-
MMBtu
|
- | - | |
05 | 3.7121: Improve handling practices | $360 | $352 | - | - | - | - | $360 | |
06 | 2.6124: Establish equipment maintenance schedule | $259 | - | - | - | - | $259 | - | |
TOTAL RECOMMENDED | $22,088 | $36,607 |
$2,217
73,857
kWh
|
$3,946
-
kW-mo/yr
|
$15,306
-
MMBtu
|
$259 | $360 | ||
TOTAL IMPLEMENTED | $8,725 | $22,865 |
$3,868
128,957
kWh
|
$4,598
-
kW-mo/yr
|
- | $259 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs