| Assessment Year | 2002 |
|---|---|
| Principal Product | Automotive Stampings |
| NAICS |
n/a
|
| SIC | 3465: Automotive Stampings |
| Sales Range | $50 M to 100M |
| # of Employees | 348 |
| Plant Area |
200,000
ft2
|
| Annual Production | 45,000
ton
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $208,511 | 9,250,776 |
kWh
|
$0.023 |
| Electricity Demand | $291,208 | 18,792 |
kW-mo/yr
|
$15.50 |
| Natural Gas | $181,954 | 20,326 |
MMBtu
|
$8.95 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $25,108 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,438 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,150 | $1,034 |
$3,077
136,750
kWh
|
$4,073
-
kW-mo/yr
|
|
| 02 | 2.4221: Install compressor air intakes in coolest locations | $2,893 | $224 |
$1,238
55,035
kWh
|
$1,655
-
kW-mo/yr
|
|
| 03 | 2.4239: Eliminate or reduce compressed air usage | $1,458 | $46 |
$44
1,949
kWh
|
$1,414
-
kW-mo/yr
|
|
| 04 | 2.4133: Use most efficient type of electric motors | $4,332 | - |
$1,867
82,986
kWh
|
$2,465
-
kW-mo/yr
|
|
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,111 | $6,493 |
$1,266
56,266
kWh
|
$1,845
-
kW-mo/yr
|
|
| 06 | 2.7135: Install occupancy sensors | $261 | $333 |
$261
11,615
kWh
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,134 | - |
$1,348
59,904
kWh
|
$1,786
-
kW-mo/yr
|
|
| 08 | 2.7111: Reduce illumination to minimum necessary levels | $2,769 | $41 |
$1,191
52,915
kWh
|
$1,578
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $25,108 | $8,171 |
$10,292
457,420
kWh
|
$14,816
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $13,438 | $1,591 |
$5,924
263,304
kWh
|
$7,514
-
kW-mo/yr
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs