ITAC Assessment: IA0291
ITAC logo
ITAC Assessment: IA0291
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Aluminum and Magnesium Castings
NAICS
n/a
SIC 3363: Aluminum Die-Castings
Sales Range $10
M
to 50
M
# of Employees 400
Plant Area 390,000
ft2
Annual Production 550,000
lb
Production Hrs. Annual 4,576
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $543,494 15,199,338
kWh
Electricity Demand $220,105 34,236
kW-mo/yr
Natural Gas $537,351 84,812
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $127,585 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $99,602

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,222 $685 $4,178
138,790
kWh
$3,044
-
kW-mo/yr
- -
02 2.4221: Install compressor air intakes in coolest locations $4,929 $920 $2,740
91,019
kWh
$2,189
-
kW-mo/yr
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $2,120 $50 $1,226
40,726
kWh
$894
-
kW-mo/yr
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,174 $682 $1,461
48,526
kWh
$713
-
kW-mo/yr
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $13,242 $25,134 $8,913
296,113
kWh
$4,329
-
kW-mo/yr
- -
06 2.4133: Use most efficient type of electric motors $4,844 $476 $2,835
94,188
kWh
$2,009
-
kW-mo/yr
- -
07 2.3131: Reschedule plant operations or reduce load to avoid peaks $6,689 $7,199 - $6,689
-
kW-mo/yr
- -
08 2.1121: Use insulation in furnaces to facilitate heating / cooling $7,328 $25,016 $7,328
243,440
kWh
- - -
09 2.1311: Replace electrically-operated equipment with fossil fuel equipment $23,689 $59,400 $31,238
1,037,807
kWh
$24,083
-
kW-mo/yr
$(-31,632.0)
-
MMBtu
-
10 4.111: Add equipment/ operators to reduce production bottleneck $55,348 $77,600 $1,641
54,522
kWh
$1,707
-
kW-mo/yr
- $52,000
TOTAL RECOMMENDED $127,585 $197,162 $61,560
2,045,131
kWh
$45,657
-
kW-mo/yr
$(-31,632.0)
-
MMBtu
$52,000
TOTAL IMPLEMENTED $99,602 $137,030 $27,635
918,072
kWh
$19,967
-
kW-mo/yr
- $52,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs