| Assessment Year | 2001 |
|---|---|
| Principal Product | Folding cartons |
| NAICS |
n/a
|
| SIC | 2657: Folding Paperboard Boxes, Including Sanitary |
| Sales Range | $10 M to 50M |
| # of Employees | 125 |
| Plant Area |
72,000
ft2
|
| Annual Production | 20,000
ton
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Minnesota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $93,727 | 2,715,549 |
kWh
|
$0.035 |
| Electricity Demand | $55,030 | 7,200 |
kW-mo/yr
|
$7.64 |
| Natural Gas | $102,807 | 11,794 |
MMBtu
|
$8.72 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $745,767 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $213,072 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $878 | $258 |
$588
17,347
kWh
|
$290
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $569 | $34 |
$381
11,232
kWh
|
$188
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $2,046 | $509 |
$1,369
40,375
kWh
|
$677
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,741 | - |
$1,168
34,446
kWh
|
$573
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,401 | $12,898 |
$3,378
99,644
kWh
|
$2,023
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4133: Use most efficient type of electric motors | $543 | - |
$364
10,727
kWh
|
$179
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.6218: Turn off equipment when not in use | $354 | $17 | - |
$354
-
kW-mo/yr
|
- | - | - | |
| 08 | 2.1222: Install turbulators | $982 | $912 | - | - |
$982
-
MMBtu
|
- | - | |
| 09 | 4.441: Install automatic packing equipment | $207,700 | $60,000 |
$(-719.0)
(-21,216)
kWh
|
$(-354.0)
-
kW-mo/yr
|
- | $208,773 | - | |
| 10 | 4.441: Install automatic packing equipment | $409,465 | $900,000 |
$(-4,261.0)
(-125,686)
kWh
|
$(-2,094.0)
-
kW-mo/yr
|
- | $415,820 | - | |
| 11 | 4.652: Replace existing equipment with more suitable substitutes | $89,568 | $135,000 | - | - | - | $50,400 | $39,168 | |
| 12 | 4.322: Eliminate old stock and modify inventory control | $26,520 | $55,500 | - | - | - | $26,520 | - | |
| TOTAL RECOMMENDED | $745,767 | $1,165,128 |
$2,268
66,869
kWh
|
$1,836
-
kW-mo/yr
|
$982
-
MMBtu
|
$701,513 | $39,168 | ||
| TOTAL IMPLEMENTED | $213,072 | $61,730 |
$1,983
58,465
kWh
|
$1,334
-
kW-mo/yr
|
$982
-
MMBtu
|
$208,773 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs