ITAC Assessment: IA0274
ITAC logo
ITAC Assessment: IA0274
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Paperboard
NAICS
n/a
SIC 2631: Paperboard Mills
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 164,062
ft2
Annual Production 50,000
ton
Production Hrs. Annual 8,736
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $613,127 23,232,000
kWh
Electricity Demand $258,742 21,120
kW-mo/yr
Natural Gas $2,708,509 453,377
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $458,528 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $110,158

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,203 $515 $3,265
125,094
kWh
$1,938
-
kW-mo/yr
-
02 2.4221: Install compressor air intakes in coolest locations $4,244 $228 $2,659
101,860
kWh
$1,585
-
kW-mo/yr
-
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,272 $50 $798
30,576
kWh
$474
-
kW-mo/yr
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $4,018 $6,398 $2,080
79,705
kWh
$1,938
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $631 - $374
14,311
kWh
$257
-
kW-mo/yr
-
06 2.7135: Install occupancy sensors $1,126 $1,530 $1,126
43,136
kWh
- -
07 2.2437: Recover waste heat from equipment $348,370 $28,600 - - $348,370
-
MMBtu
08 2.2135: Repair and eliminate steam leaks $20,113 $2,400 - - $20,113
-
MMBtu
09 2.2135: Repair and eliminate steam leaks $11,081 $1,060 - - $11,081
-
MMBtu
10 2.1213: Direct warmest air to combustion intake $31,235 $6,000 - - $31,235
-
MMBtu
11 2.1233: Analyze flue gas for proper air/fuel ratio $31,235 $5,000 - - $31,235
-
MMBtu
TOTAL RECOMMENDED $458,528 $51,781 $10,302
394,682
kWh
$6,192
-
kW-mo/yr
$442,034
-
MMBtu
TOTAL IMPLEMENTED $110,158 $23,181 $10,302
394,682
kWh
$6,192
-
kW-mo/yr
$93,664
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs