| Assessment Year | 2001 |
|---|---|
| Principal Product | Aluminum and Brass Castings |
| NAICS |
n/a
|
| SIC | 3365: Aluminum Foundries |
| Sales Range | $10 M to 50M |
| # of Employees | 130 |
| Plant Area |
76,324
ft2
|
| Annual Production | 1,400,000
lb
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $58,230 | 2,454,620 |
kWh
|
$0.024 |
| Electricity Demand | $67,689 | 9,516 |
kW-mo/yr
|
$7.11 |
| Natural Gas | $28,440 | 6,636 |
MMBtu
|
$4.29 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $102,467 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,366 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $587 | - |
$230
9,685
kWh
|
$357
-
kW-mo/yr
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $303 | $24 |
$116
4,914
kWh
|
$187
-
kW-mo/yr
|
- | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $118 | $165 |
$50
2,098
kWh
|
$68
-
kW-mo/yr
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $661 | $3,371 |
$253
10,660
kWh
|
$408
-
kW-mo/yr
|
- | |
| 05 | 4.111: Add equipment/ operators to reduce production bottleneck | $100,798 | $400,189 | n/a |
$(-882.0)
(-37,232)
kWh
|
$(-1,520.0)
-
kW-mo/yr
|
$103,200 |
| TOTAL RECOMMENDED | $102,467 | $403,749 |
$(-233.0)
(-9,875)
kWh
|
$(-500.0)
-
kW-mo/yr
|
$103,200 | ||
| TOTAL IMPLEMENTED | $1,366 | $3,536 |
$533
22,443
kWh
|
$833
-
kW-mo/yr
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs