ITAC Assessment: IA0266
ITAC logo
ITAC Assessment: IA0266
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product coated paper products
NAICS
n/a
SIC 2672: Coated and Laminated Paper, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 190
Plant Area 250,000
ft2
Annual Production 2,704,000
thousand feet
Production Hrs. Annual 8,640
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $507,083 17,348,854
kWh
Electricity Demand $215,842 30,384
kW-mo/yr
Natural Gas $1,191,468 335,794
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $493,639 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $264,205

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.2437: Recover waste heat from equipment $26,215 $35,700 - - $26,215
-
MMBtu
- -
02 2.7314: Reduce ventilation air $12,703 $5,038 $2,664
91,232
kWh
$812
-
kW-mo/yr
$9,227
-
MMBtu
- -
03 2.4133: Use most efficient type of electric motors $8,737 - $6,673
228,543
kWh
$2,064
-
kW-mo/yr
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $7,175 $11,846 $5,059
173,268
kWh
$2,116
-
kW-mo/yr
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $6,933 - $5,298
181,440
kWh
$1,635
-
kW-mo/yr
- - -
06 2.7135: Install occupancy sensors $2,034 $1,663 $2,034
69,652
kWh
- - - -
07 2.7135: Install occupancy sensors $1,804 $5,398 $1,804
61,769
kWh
- - - -
08 2.7313: Recycle air for heating, ventilation and air conditioning $6,440 $3,410 - - $6,440
-
MMBtu
- -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,027 $518 $7,659
262,308
kWh
$2,368
-
kW-mo/yr
- - -
10 2.4221: Install compressor air intakes in coolest locations $3,165 $585 $2,419
82,828
kWh
$746
-
kW-mo/yr
- - -
11 2.1233: Analyze flue gas for proper air/fuel ratio $1,767 $2,000 - - $1,767
-
MMBtu
- -
12 3.5212: Regrind, reuse, or sell scrap plastic parts $123,691 $50,000 $(-787.0)
(-26,943)
kWh
$(-3,922.0)
-
kW-mo/yr
- $128,400
-
lb
-
13 4.453: Reschedule breaks to allow for continuous production $231,300 - - - - - $231,300
14 4.322: Eliminate old stock and modify inventory control $51,648 $32,000 - - - $24,000
-
lb
$27,648
TOTAL RECOMMENDED $493,639 $148,158 $32,823
1,124,097
kWh
$5,819
-
kW-mo/yr
$43,649
-
MMBtu
$152,400
-
lb
$258,948
TOTAL IMPLEMENTED $264,205 $16,612 $23,844
816,599
kWh
$7,294
-
kW-mo/yr
$1,767
-
MMBtu
- $231,300
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs