ITAC Assessment: IA0263
ITAC logo
ITAC Assessment: IA0263
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product packaging equipment
NAICS
n/a
SIC 3565: Packaging Machinery
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 160,000
ft2
Annual Production 475
ton
Production Hrs. Annual 6,240
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $46,036 1,597,320
kWh
Electricity Demand $42,150 3,888
kW-mo/yr
Natural Gas $16,249 3,673
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $172,863 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $166,464

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,869 $1,014 $2,825
98,090
kWh
$2,044
-
kW-mo/yr
-
02 2.4235: Remove or close off unneeded compressed air lines $2,475 - $1,034
35,893
kWh
$1,441
-
kW-mo/yr
-
03 2.4221: Install compressor air intakes in coolest locations $648 $125 $377
13,103
kWh
$271
-
kW-mo/yr
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,382 - $1,961
68,016
kWh
$1,421
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,744 $4,539 $950
32,994
kWh
$794
-
kW-mo/yr
-
06 2.4133: Use most efficient type of electric motors $625 - $299
10,377
kWh
$326
-
kW-mo/yr
-
07 4.421: Modify current incentive program $84,240 - - - $84,240
08 4.421: Modify current incentive program $74,880 - - - $74,880
TOTAL RECOMMENDED $172,863 $5,678 $7,446
258,473
kWh
$6,297
-
kW-mo/yr
$159,120
TOTAL IMPLEMENTED $166,464 $1,014 $3,859
133,983
kWh
$3,485
-
kW-mo/yr
$159,120
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs