| Assessment Year | 2000 |
|---|---|
| Principal Product | livestock food supplements |
| NAICS |
n/a
|
| SIC | 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 150 |
| Plant Area |
180,000
ft2
|
| Annual Production | 45,000
ton
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $136,931 | 3,644,197 |
kWh
|
$0.038 |
| Electricity Demand | $42,359 | 7,188 |
kW-mo/yr
|
$5.89 |
| Natural Gas | $20,985 | 4,099 |
MMBtu
|
$5.12 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $406,159 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $12,467 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,574 | $8,062 |
$2,751
106,682
kWh
|
$1,823
-
kW-mo/yr
|
- | - | - | - | - | |
| 02 | 2.7111: Reduce illumination to minimum necessary levels | $1,401 | $144 |
$879
33,998
kWh
|
$522
-
kW-mo/yr
|
- | - | - | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,260 | - |
$793
30,774
kWh
|
$467
-
kW-mo/yr
|
- | - | - | - | - | |
| 04 | 2.7135: Install occupancy sensors | $670 | $665 |
$670
25,791
kWh
|
- | - | - | - | - | - | |
| 05 | 2.2437: Recover waste heat from equipment | $2,240 | $2,514 | - | - |
$2,240
-
MMBtu
|
- | - | - | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $880 | $163 |
$558
21,688
kWh
|
$322
-
kW-mo/yr
|
- | - | - | - | - | |
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $358 | $25 |
$225
8,792
kWh
|
$133
-
kW-mo/yr
|
- | - | - | - | - | |
| 08 | 3.4111: Use closed cycle process to minimize waste water production | $4,942 | $4,463 | - | - |
$3,161
-
MMBtu
|
$879
-
Tgal
|
- | - |
$902
-
Tgal
|
|
| 09 | 3.3128: Utilize other methods to remove contaminants | $323,237 | $750,000 |
$(-16,814.0)
(-651,817)
kWh
|
$(-9,949.0)
-
kW-mo/yr
|
- | - | - | $350,000 | - | |
| 10 | 3.3128: Utilize other methods to remove contaminants | $43,847 | $35,000 |
$(-353.0)
(-13,482)
kWh
|
- | - | - | $13,000 | $31,200 | - | |
| 11 | 4.322: Eliminate old stock and modify inventory control | $22,750 | $50,000 | - | - | - | - | $22,750 | - | - | |
| TOTAL RECOMMENDED | $406,159 | $851,036 |
$(-11,291.0)
(-437,574)
kWh
|
$(-6,682.0)
-
kW-mo/yr
|
$5,401
-
MMBtu
|
$879
-
Tgal
|
$35,750 | $381,200 |
$902
-
Tgal
|
||
| TOTAL IMPLEMENTED | $12,467 | $13,497 |
$4,858
188,159
kWh
|
$2,667
-
kW-mo/yr
|
$3,161
-
MMBtu
|
$879
-
Tgal
|
- | - |
$902
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs