Assessment Year | 1999 |
---|---|
Principal Product | washing machine transmissions |
NAICS |
n/a
|
SIC | 3633: Household Laundry Equipment |
Sales Range | $10 M to 50M |
# of Employees | 170 |
Plant Area |
75,000
ft2
|
Annual Production | 950,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $131,980 | 5,129,250 |
kWh
|
$0.026 |
Electricity Demand | $193,716 | 14,256 |
kW-mo/yr
|
$13.59 |
Natural Gas | $35,638 | 8,070 |
MMBtu
|
$4.42 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $301,349 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $107,337 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,846 | $13,626 |
$4,163
162,075
kWh
|
$4,683
-
kW-mo/yr
|
- | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $2,935 | $579 |
$1,460
56,858
kWh
|
$1,475
-
kW-mo/yr
|
- | - | - | |
03 | 2.7135: Install occupancy sensors | $708 | $1,264 |
$708
27,550
kWh
|
- | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $742 | $764 |
$369
14,361
kWh
|
$373
-
kW-mo/yr
|
- | - | - | |
05 | 3.4111: Use closed cycle process to minimize waste water production | $14,369 | $4,297 |
$(-144.0)
(-5,569)
kWh
|
$(-121.0)
-
kW-mo/yr
|
$17,134
-
Tgal
|
$(-2,500.0) | - | |
06 | 4.111: Add equipment/ operators to reduce production bottleneck | $176,000 | $575,000 | - | - | - | $176,000 | - | |
07 | 3.1161: Eliminate/reduce an operation | $97,749 | $800 | - | - | - | $38,184 | $59,565 | |
TOTAL RECOMMENDED | $301,349 | $596,330 |
$6,556
255,275
kWh
|
$6,410
-
kW-mo/yr
|
$17,134
-
Tgal
|
$211,684 | $59,565 | ||
TOTAL IMPLEMENTED | $107,337 | $15,190 |
$4,532
176,436
kWh
|
$5,056
-
kW-mo/yr
|
- | $38,184 | $59,565 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs