Assessment Year | 1998 |
---|---|
Principal Product | aviation electronics components |
NAICS |
n/a
|
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 375 |
Plant Area |
54,000
ft2
|
Annual Production | 162,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $91,752 | 3,643,318 |
kWh
|
$0.025 |
Electricity Demand | $118,043 | 8,544 |
kW-mo/yr
|
$13.82 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $234,631 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $178,161 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,263 | $51,347 |
$5,286
211,606
kWh
|
$7,977
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,633 | $3,261 |
$1,248
49,824
kWh
|
$1,385
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $67 | $100 |
$34
1,465
kWh
|
$33
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $356 | $950 |
$181
7,327
kWh
|
$175
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $211 | $310 |
$106
4,103
kWh
|
$105
-
kW-mo/yr
|
- | - | - | - | |
06 | 4.111: Add equipment/ operators to reduce production bottleneck | $15,860 | $400 | - | - | - | $(-6,240.0) | - | $22,100 | |
07 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,680 | $5,250 | - | - | - | - | - | $1,680 | |
08 | 4.131: Modify process to reduce material use/cost | $119,822 | $290,000 | - | - | - | $100,000 | $19,822 | - | |
09 | 4.513: Re-arrange equipment layout to reduce labor costs | $42,573 | $15,000 |
$71
2,931
kWh
|
- |
$957
-
Tgal
|
$25,000 | $16,545 | - | |
10 | 3.1161: Eliminate/reduce an operation | $38,166 | $2,000 |
$4,339
173,505
kWh
|
- |
$4,100
-
Tgal
|
$25,000 | $4,727 | - | |
TOTAL RECOMMENDED | $234,631 | $368,618 |
$11,265
450,761
kWh
|
$9,675
-
kW-mo/yr
|
$5,057
-
Tgal
|
$143,760 | $41,094 | $23,780 | ||
TOTAL IMPLEMENTED | $178,161 | $300,911 |
$5,587
223,329
kWh
|
$1,385
-
kW-mo/yr
|
$4,100
-
Tgal
|
$118,760 | $24,549 | $23,780 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs